Friday, December 30, 2016

Today's work on/in the business - Thurs 29 December

1. Update my record of time worked. (5mins)
2. Review progress made this week. (15mins)
3. More time spent searching for backup of customer's previous website - still unsuccessful - SQL entries not on our server. (10mins)
4. Working on restoring our mail server after the hard drive failed again - identified step that was not in documentation. (10mins)

I just could not get into work mode!

Thursday, December 29, 2016

Today's work on/in the business - Wed 28 December

1. Working on restoring our mail server after the hard drive failed again. (1hr 50mins)
2. Update my record of time worked. (15mins)
3. Review progress made last week and ensure the schedule is right for this week. (30mins)
4. Working on process for new Events setup - review events. (45mins)
5. Review the project schedules, adjusted all projects based on actual progress and added a week to software schedules. (5mins)
6. Backup mail locally. (20mins)

Wednesday, December 28, 2016

Today's work on/in the business - Fri 23 December

1. Investigate process for next version of software project for new customer - investigation for new process, particularly use of a proxy. (4hrs 50mins)
2. Update my record of time worked. (10mins)
3. Review progress made this week. (20mins)
4. Working on process for new Events setup - review events and enter regular events. (1hr)

A fairly unhurried last day of work before Christmas - then a lovely Christmas Day with family!

Friday, December 23, 2016

Today's work on/in the business - Thurs 22 December

1. Investigate process for next version of software project for new customer - investigation for new process, particularly use of a proxy. (1hr 40mins)
2. Update my record of time worked. (15mins)
3. Review progress made this week. (15mins)
4. Preparation for next session with new student after problems with creating documents on my laptop, and next session, including travel time. (5hrs 45mins)

Thursday, December 22, 2016

Today's work on/in the business - Wed 21 December

1. Update my record of time worked. (5mins)
2. Review progress made this week. (15mins)
3. Working on process for new Events setup - address issue with site. (10mins)
4. Review access to system and put up temporary page. (1hr 50mins)
5. Investigate process for next version of software project for new customer - investigation for new process, particularly use of a proxy. (2hrs 20mins)
6. Preparation for next session with new student - problems with creating documents on my laptop. (3hrs 45mins)

Wednesday, December 21, 2016

Today's work on/in the business - Tues 20 December

1. Update my record of time worked. (5mins)
2. Review progress made this week. (15mins)
3. Investigate process for next version of software project for new customer - investigation for new process, particularly use of a proxy. (4hrs 10mins)
4. Next session with new student, including preparation and travel time. (3hrs 30mins)

Tuesday, December 20, 2016

Today's work on/in the business - Mon 19 December

1. Update my record of time worked. (5mins)
2. Review progress made last week and ensure the schedule is right for this week. (25mins)
3. Review the project schedules, adjusted all projects based on actual progress and added a week to software schedules. (5mins)
4. Backup mail locally. (15mins)
5. Investigate process for next version of software project for new customer - investigation for new process, particularly use of a proxy. (6hrs 5mins)
6. Top up mobile phone. (10mins)

Monday, December 19, 2016

Today's work on/in the business - Fri 16 December

1. Update my record of time worked. (5mins)
2. Review progress made this week. (15mins)
3. Investigate process for next version of software project for new customer - investigation for new process, particularly use of a proxy. (7hrs 35mins)

Friday, December 16, 2016

Today's work on/in the business - Thurs 15 December

1. Update my record of time worked. (5mins)
2. Review progress made this week. (15mins)
3. Investigate process for next version of software project for new customer - investigation for new process, particularly use of a proxy. (6hrs 25mins)
4. Top up mobile broadband. (5mins)
5. Next session with new student, including travel time. (3hrs 45mins)

Thursday, December 15, 2016

Today's work on/in the business - Wed 14 December

1. Update my record of time worked. (5mins)
2. Review progress made this week. (15mins)
3. Investigate process for next version of software project for new customer - investigation for new process, particularly use of a proxy. (7hrs 35mins)

Wednesday, December 14, 2016

Today's work on/in the business - Tues 13 December

1. Update my record of time worked. (5mins)
2. Review progress made this week. (10mins)
3. Working on process for new Events setup - address issue then generate and download full backup of site. (1hr 15mins)
4. Investigate process for next version of software project for new customer - investigation for new process, particularly use of a proxy. (3hrs 35mins)
5. More time spent searching for backup of customer's previous website - still unsuccessful. (3hrs 10mins)

Tuesday, December 13, 2016

Today's work on/in the business - Mon 12 December

1. Update my record of time worked. (5mins)
2. Review progress made last week and ensure the schedule is right for this week. (20mins)
3. Review the project schedules, adjusted all projects based on actual progress and added a week to software schedules. (5mins)
4. Backup mail locally. (10mins)
5. Investigate process for next version of software project for new customer - investigation for new process, particularly use of a proxy. (8hrs 10mins)
6. Working on process for new Events setup - generate backup of site before addressing issue. (5mins)

Monday, December 12, 2016

Today's work on/in the business - Fri 9 December

1. Update my record of time worked. (5mins)
2. Review progress made this week. (15mins)
3. Investigate process for next version of software project for new customer - investigation for new process, particularly use of a proxy. (6hrs 50mins)

Friday, December 9, 2016

Today's work on/in the business - Thurs 8 December

1. Update my record of time worked. (5mins)
2. Review progress made this week. (20mins)
3. Investigate process for next version of software project for new customer - investigation for new process, particularly use of a proxy. (7hrs 25mins)
4. Skype meeting to discuss website update for customer - includes time spent searching for backup of her site (unsuccessful so far). (50mins)

Thursday, December 8, 2016

Today's work on/in the business - Wed 7 December

1. Update my record of time worked. (5mins)
2. Review progress made this week. (5mins)
3. Working on process for new Events setup - review events. (10mins)
4. Investigate process for next version of software project for new customer - investigation for new process, particularly use of a proxy. (7hrs 45mins)

Wednesday, December 7, 2016

Today's work on/in the business - Tues 6 December

1. Update my record of time worked. (5mins)
2. Review progress made this week. (10mins)
3. Investigate process for next version of software project for new customer - investigation for new process, particularly use of a proxy. (8hrs 40mins)

Tuesday, December 6, 2016

Today's work on/in the business - Mon 5 December

1. Update my record of time worked. (5mins)
2. Backup mail locally. (10mins)
3. Review progress made last week and ensure the schedule is right for this week. (20mins)
4. Review the project schedules, adjusted all projects based on actual progress and added a week to software schedules. (5mins)
5. Talk to support for new phone, get a replacement SIM for the new phone (includes doing some shopping). (1hr 45mins)
6. Working on process for new Events setup - review events and enter regular events. (5mins)

Monday, December 5, 2016

Today's work on/in the business - Fri 2 December

1. Update my record of time worked. (5mins)
2. Review progress made this week. (5mins)
3. Investigate process for next version of software project for new customer - investigation for new process, particularly use of a proxy. (6hrs 10mins)
4. Buy a new phone, transfer contacts to laptop, get passwords. (1hr 45mins)
5. Working on process for new Events setup - review events. (10mins)

Friday, December 2, 2016

Today's work on/in the business - Thurs 1 December

1. Update my record of time worked. (10mins)
2. Review progress made this week. (5mins)
3. Investigate process for next version of software project for new customer - investigation for new process, particularly use of a proxy. (7hrs 45mins)
4. Working on process for new Events setup - review events. (35mins)

Thursday, December 1, 2016

Today's work on/in the business - Wed 30 November

1. Update my record of time worked. (5mins)
2. Review progress made this week. (15mins)
3. Investigate process for next version of software project for new customer - investigation for new process, particularly use of a proxy. (8hrs 45mins)

Wednesday, November 30, 2016

Today's work on/in the business - Tues 29 November

1. Update my record of time worked. (5mins)
2. Review progress made this week. (15mins)
3. Investigate process for next version of software project for new customer - investigation for new process, particularly use of a proxy. (2hrs 55mins)
4. Working on process for new Events setup - review events and investigate domain issue. (45mins)
5. Next session with new student, including travel time. (2hrs 50mins)

Tuesday, November 29, 2016

Today's work on/in the business - Mon 28 November

1. Update my record of time worked. (5mins)
2. Review progress made last week and ensure the schedule is right for this week. (35mins)
3. Review the project schedules, adjusted all projects based on actual progress and added a week to software schedules. (5mins)
4. Backup mail locally. (20mins)
5. Investigate process for next version of software project for new customer - investigation for new process, particularly use of a proxy. (2hrs 55mins)
6. Preparation for next session with new student. (2hrs 35mins)
7. Working on process for new Events setup - review events and enter regular events. (1hr 15mins)

Monday, November 28, 2016

Today's work on/in the business - Thurs 24 November

1. Update my record of time worked. (5mins)
2. Review progress made this week. (10mins)
3. Investigate process for next version of software project for new customer - investigation for new process, particularly use of a proxy. (8hrs)

Friday was a write off - a good friend's memorial service, catching up with some people I have not seen in far too long... too much emotion to come back and achieve anything. RIP Hugh.

Thursday, November 24, 2016

Today's work on/in the business - Wed 23 November

1. Update my record of time worked. (10mins)
2. Review progress made this week. (15mins)
3. Investigate process for next version of software project for new customer - investigation for new process, particularly use of a proxy. (7hrs 10mins)
4. Top up mobile phone. (5mins)

Wednesday, November 23, 2016

Today's work on/in the business - Tues 22 November

1. Investigate process for next version of software project for new customer - investigation for new process, particularly use of a proxy - includes on site meeting and travel there and back. (5hrs 40mins)
2. Update my record of time worked. (5mins)
3. Review progress made this week. (10mins)
4. Preparation and first session with new student. (3hrs 20mins)

Tuesday, November 22, 2016

Today's work on/in the business - Mon 21 November

1. Update my record of time worked. (5mins)
2. Review progress made last week and ensure the schedule is right for this week. (20mins)
3. Review the project schedules, adjusted all projects based on actual progress and added a week to software schedules. (5mins)
4. Backup mail locally. (10mins)
5. Investigate process for next version of software project for new customer - investigation for new process, particularly use of a proxy. (9hrs 20mins)

Monday, November 21, 2016

Today's work on/in the business - Fri 18 November

1. Update my record of time worked. (5mins)
2. Review progress made this week. (10mins)
3. Investigate process for next version of software project for new customer - investigation for new process, particularly use of a proxy. (7hrs 45mins)
4. Calls re new student to tutor. (5mins)

Friday, November 18, 2016

Today's work on/in the business - Thurs 17 November

1. Update my record of time worked. (5mins)
2. Review progress made this week. (10mins)
3. Investigate process for next version of software project for new customer - investigation for new process, particularly use of a proxy. (6hrs 30mins)

Thursday, November 17, 2016

Today's work on/in the business - Wed 16 November

1. Update my record of time worked. (5mins)
2. Review progress made this week. (10mins)
3. Investigate process for next version of software project for new customer - investigation for new process, particularly use of a proxy. (9hrs 5mins)

Wednesday, November 16, 2016

Today's work on/in the business - Tues 15 November

1. Update my record of time worked. (5mins)
2. Review progress made this week. (20mins)
3. Investigate process for next version of software project for new customer - investigation for new process, particularly use of a proxy. (9hrs 15mins)
4. Top up mobile broadband. (5mins)
5. Follow up for tutorial. (15mins)

Tuesday, November 15, 2016

Today's work on/in the business - Mon 14 November

1. Update my record of time worked. (5mins)
2. Review progress made last week and ensure the schedule is right for this week. (15mins)
3. Review the project schedules, adjusted all projects based on actual progress and added a week to software schedules. (5mins)
4. Backup mail locally. (5mins)
5. Next tutorial - including preparation and follow up time. (8hrs 5mins)
6. Investigate process for next version of software project for new customer - investigation for new process, particularly use of a proxy. (2hrs 50mins)
7. Working on process for new Events setup - review events. (15mins)

Monday, November 14, 2016

Today's work on/in the business - Sun 13 November

1. Update my record of time worked. (10mins)
2. Review progress made this week. (10mins)
3. Investigate process for next version of software project for new customer - investigation for new process, particularly use of a proxy. (7hrs 30mins)

Sunday, November 13, 2016

Today's work on/in the business - Sat 12 November

1. Backup files from my laptop (which got knocked onto the floor a few days ago) to the NAS. (6hrs 50mins) - at the same time as other work was happening.
2. Update my record of time worked. (10mins)
3. Review progress made this week - including recertifying Notes Ids and trying to transfer them to the new laptop. (50mins)
4. Investigate process for next version of software project for new customer - investigation for new process, particularly use of a proxy. (6hrs)

Saturday, November 12, 2016

Today's work on/in the business - Fri 11 November

1. Update my record of time worked. (5mins)
2. Review progress made this week. (15mins)
3. Investigate process for next version of software project for new customer - investigation for new process, particularly use of a proxy. (8hrs 50mins)

Friday, November 11, 2016

Today's work on/in the business - Thurs 10 November

1. Update my record of time worked. (5mins)
2. Review progress made this week. (10mins)
3. Investigate process for next version of software project for new customer - investigation for new process, particularly use of a proxy. (10hrs 15mins)

Thursday, November 10, 2016

Today's work on/in the business - Wed 9 November

1. Update my record of time worked. (5mins)
2. Review progress made this week. (5mins)
3. Investigate process for next version of software project for new customer - investigation for new process, particularly use of a proxy. (8hrs)

Wednesday, November 9, 2016

Today's work on/in the business - Tues 8 November

1. Update my record of time worked. (5mins)
2. Review progress made this week. (5mins)
3. Working on process for new Events setup - review events. (15mins)
4. Investigate process for next version of software project for new customer - investigation for new process, particularly use of a proxy. (7hrs 35mins)

Then out for a lovely night of music!

Tuesday, November 8, 2016

Today's work on/in the business - Mon 7 November

1. Update my record of time worked. (5mins)
2. Review progress made last week and ensure the schedule is right for this week. (15mins)
3. Review the project schedules, adjusted all projects based on actual progress and added a week to software schedules. (5mins)
4. Backup mail locally. (10mins)
5. Investigate process for next version of software project for new customer - investigation for new process, particularly use of a proxy. (7hrs 35mins)

Monday, November 7, 2016

Today's work on/in the business - Fri 4 November

1. Update my record of time worked. (5mins)
2. Review progress made this week. (5mins)
3. Working on process for new Events setup - review events. (40mins)
4. Investigate process for next version of software project for new customer - investigation for new process, particularly use of a proxy. (5hrs 50mins)

Friday, November 4, 2016

Today's work on/in the business - Thurs 3 November

1. Update my record of time worked. (5mins)
2. Review progress made this week. (5mins)
3. Investigate process for next version of software project for new customer - investigation for new process, particularly use of a proxy. (10hrs 20mins)
4. Backup mail locally. (5mins)

Thursday, November 3, 2016

Today's work on/in the business - Wed 2 November

1. Update my record of time worked. (10mins)
2. Review progress made this week. (20mins)
3. Investigate process for next version of software project for new customer - investigation for new process, particularly use of a proxy. (7hrs 35mins)

Wednesday, November 2, 2016

Today's work on/in the business - Tues 1 November

1. Investigate process for next version of software project for new customer - investigation for new process, particularly use of a proxy. (25mins)

After all, it was a public holiday.... So I only did the bare minimum I had promised to do...

Today's work on/in the business - Mon 31 October

1. Update my record of time worked. (5mins)
2. Review progress made last week and ensure the schedule is right for this week. (20mins)
3. Review the project schedules, adjusted all projects based on actual progress and added a week to software schedules. (5mins)
4. Backup mail locally - not possible as mail server broken by Linux update. (5mins)
5. Working on process for new Events setup - review events and enter regular events. (1hr 35mins)
6. Working on fixing our mail server after Linux update broke it. (4hrs 10mins)
7. Investigate process for next version of software project for new customer - investigation for new process, particularly use of a proxy. (1hr 35mins)

Monday, October 31, 2016

Today's work on/in the business - Fri 28 October

1. Update my record of time worked. (5mins)
2. Review progress made this week. (15mins)
3. Investigate process for next version of software project for new customer - investigation for new process, particularly use of a proxy. (7hrs 45mins)
4. Working on process for new Events setup - review events. (5mins)

Friday, October 28, 2016

Today's work on/in the business - Thurs 27 October

1. Update my record of time worked. (5mins)
2. Review progress made this week. (5mins)
3. Investigate process for next version of software project for new customer - investigation for new process, particularly use of a proxy. (10hrs 25mins)

Thursday, October 27, 2016

Today's work on/in the business - Wed 26 October

1. Update my record of time worked. (5mins)
2. Review progress made this week. (10mins)
3. Investigate process for next version of software project for new customer - investigation for new process, particularly use of a proxy. (9hrs 35mins)

Wednesday, October 26, 2016

Today's work on/in the business - Tues 25 October

1. Update my record of time worked. (5mins)
2. Review progress made this week. (10mins)
3. Working on process for new Events setup - review events. (10mins)
4. Investigate process for next version of software project for new customer - investigation for new process, particularly use of a proxy. (6hrs 35mins)

Tuesday, October 25, 2016

Today's work on/in the business - Mon 24 October

1. Update my record of time worked. (10mins)
2. Review progress made last week and ensure the schedule is right for this week. (25mins)
3. Review the project schedules, adjusted all projects based on actual progress and added a week to software schedules. (5mins)
4. Backup mail locally. (15mins)
5. Investigate process for next version of software project for new customer - investigation for new process, particularly use of a proxy. (1hr 20mins)
6. Accounting - continue setting up new free accounting software. (6hrs 40mins)

Monday, October 24, 2016

Today's work on/in the business - Fri 21 October

1. Update my record of time worked. (10mins)
2. Review progress made this week. (15mins)
3. Investigate process for next version of software project for new customer - investigation for new process, particularly use of a proxy. (2hrs 15mins)
4. Accounting - continue setting up new free accounting software. (5hrs 5mins)

Friday, October 21, 2016

Today's work on/in the business - Thurs 20 October

1. Update my record of time worked. (5mins)
2. Review progress made this week. (15mins)
3. Accounting - continue setting up new free accounting software. (1hr 15mins)
4. Investigate process for next version of software project for new customer - investigation for new process, particularly use of a proxy. (5hrs 5mins)

Thursday, October 20, 2016

Today's work on/in the business - Wed 19 October

1. Update my record of time worked. (5mins)
2. Review progress made this week. (5mins)
3. Investigate process for next version of software project for new customer - investigation for new process, particularly use of a proxy. (5hrs 10mins)
4. Accounting - continue setting up new free accounting software. (3hrs 45mins)

Wednesday, October 19, 2016

Today's work on/in the business - Tues 18 October

1. Update my record of time worked. (5mins)
2. Review progress made this week. (20mins)
3. Accounting - continue setting up new free accounting software. (6hrs 25mins)
4. Investigate process for next version of software project for new customer - investigation for new process, particularly use of a proxy. (1hr 15mins)

Tuesday, October 18, 2016

Today's work on/in the business - Mon 17 October

1. Update my record of time worked. (10mins)
2. Review progress made last week and ensure the schedule is right for this week. (20mins)
3. Review the project schedules, adjusted all projects based on actual progress and added a week to software schedules. (5mins)
4. Backup mail locally. (10mins)
5. Accounting - continue setting up new free accounting software. (8hrs 20mins)

Monday, October 17, 2016

Today's work on/in the business - Fri 14 October

1. Update my record of time worked. (5mins)
2. Review progress made this week. (10mins)
3. Working on process for new Events setup - review events. (10mins)
4. Investigate process for next version of software project for new customer - investigation for new process, particularly use of a proxy. (55mins)
5. Accounting - continue setting up new free accounting software. (4hrs 25mins)

Friday, October 14, 2016

Today's work on/in the business - Thurs 13 October

1. Update my record of time worked. (5mins)
2. Review progress made this week. (15mins)
3. Accounting - continue setting up new free accounting software. (3hrs 55mins)
4. Calls re new student to tutor and emails re existing one. (15mins)

Plus a visit from an old friend for coffee, shopping and collecting motorbike part that was in for work.

Thursday, October 13, 2016

Today's work on/in the business - Wed 12 October

1. Update my record of time worked. (5mins)
2. Review progress made this week. (20mins)
3. Accounting - continue setting up new free accounting software. (6hrs 50mins)
4. Assisting with identifying and fixing the issue on our server after updates and reboot. (25mins)

Wednesday, October 12, 2016

Today's work on/in the business - Tues 11 October

1. Update my record of time worked. (5mins)
2. Review progress made this week. (10mins)
3. Working on process for new Events setup - review events. (10mins)
4. Accounting - continue setting up new free accounting software. (5hrs 45mins)
5. Investigate process for next version of software project for new customer - investigation for new process, particularly use of a proxy. (40mins)
6. Call for a new student to tutor - left voice mail message. (15mins)

Tuesday, October 11, 2016

Today's work on/in the business - Mon 10 October

1. Update my record of time worked. (5mins)
2. Review progress made last week and ensure the schedule is right for this week. (20mins)
3. Review the project schedules, adjusted all projects based on actual progress and added a week to software schedules. (5mins)
4. Backup mail locally. (15mins)
5. Working on process for new Events setup - review events. (25mins)
6. Investigate process for next version of software project for new customer - investigation for new process, particularly use of a proxy. (1hr)
7. Accounting - continue setting up new free accounting software. (5hrs 15mins)

Monday, October 10, 2016

Today's work on/in the business - Fri 7 October

1. Update my record of time worked. (10mins)
2. Review progress made this week. (10mins)
3. Accounting - continue setting up new free accounting software. (4hrs 35mins)

Then a good friend arrived to stay overnight - great to catch up with her - Darwin's a long way away!

Friday, October 7, 2016

Today's work on/in the business - Thurs 6 October

1. Update my record of time worked. (5mins)
2. Review progress made this week. (10mins)
3. Investigate process for next version of software project for new customer - investigation for new process, particularly use of a proxy. (45mins)
4. Accounting - continue setting up new free accounting software. (3hrs 15mins)
5. Next tutorial - including final preparation time. (4hrs 15mins)

Thursday, October 6, 2016

Today's work on/in the business - Wed 5 October

1. Update my record of time worked. (5mins)
2. Review progress made this week. (15mins)
3. Investigate process for next version of software project for new customer - investigation for new process, particularly use of a proxy. (1hr 45mins)
4. Accounting - continue setting up new free accounting software. (3hrs 40mins)
5. Preparation for next tutorial. (2hrs 25mins)

Wednesday, October 5, 2016

Today's work on/in the business - Tues 4 October

1. Update my record of time worked. (5mins)
2. Review progress made this week. (5mins)
3. Investigate process for next version of software project for new customer - investigation for new process, particularly use of a proxy. (4hrs 10mins)
4. Accounting - continue setting up new free accounting software. (4hrs 45mins)

Tuesday, October 4, 2016

Today's work on/in the business - Mon 3 October

1. Update my record of time worked. (10mins)
2. Review progress made last week and ensure the schedule is right for this week. (20mins)
3. Backup mail locally. (20mins)
4. Review the project schedules, adjusted all projects based on actual progress and added a week to software schedules. (5mins)
5. Investigate process for next version of software project for new customer - investigation for new process, particularly use of a proxy. (5hrs 45mins)

Monday, October 3, 2016

Today's work on/in the business - Fri 30 September

1. Update my record of time worked. (5mins)
2. Review progress made this week. (10mins)
3. Investigate process for next version of software project for new customer - investigation for new process, particularly use of a proxy. (1hr 35mins)
4. Search for contract work. (2hrs)

It was after all officially a public holiday...

Friday, September 30, 2016

Today's work on/in the business - Thurs 29 September

1. Update my record of time worked. (5mins)
2. Review progress made this week. (30mins)
3. Investigate process for next version of software project for new customer - investigation for new process, particularly use of a proxy. (7hrs 40mins)

Thursday, September 29, 2016

Today's work on/in the business - Wed 28 September

1. Update my record of time worked. (5mins)
2. Review progress made this week. (15mins)
3. Working on process for new Events setup - review events. (5mins)
4. Investigate process for next version of software project for new customer - investigation for new process, particularly use of a proxy. (7hrs 25mins)
5. Search for contract work. (40mins)

Wednesday, September 28, 2016

Today's work on/in the business - Tues 27 September

1. Update my record of time worked. (10mins)
2. Review progress made this week. (25mins)
3. Working on process for new Events setup - review events. (10mins)
4. Investigate process for next version of software project for new customer - investigation for new process, particularly use of a proxy. (6hrs 40mins)

Tuesday, September 27, 2016

Today's work on/in the business - Mon 26 September

1. Update my record of time worked. (15mins)
2. Review progress made last week and ensure the schedule is right for this week. (25mins)
3. Review the project schedules, adjusted all projects based on actual progress and added a week to software schedules. (5mins)
4. Backup mail locally. (20mins)
5. Working on process for new Events setup - review events and enter regular events. (2hrs 50mins)
6. Investigate process for next version of software project for new customer - investigation for new process, particularly use of a proxy. (1hr 20mins)

Monday, September 26, 2016

Today's work on/in the business - Sat 24 September

1. Update my record of time worked. (5mins)
2. Review progress made this week. (15mins)
3. Accounting - continue setting up new free accounting software. (45mins)

And Sunday was a wonderful friend's 60th Birthday celebration - with lots of music, catching up with old friends and meeting new ones!

Saturday, September 24, 2016

Today's work on/in the business - Fri 23 September

1. Update my record of time worked. (10mins)
2. Review progress made this week. (10mins)
3. Next tutorial - including final preparation time. (2hrs 50mins)
4. Investigate process for next version of software project for new customer - investigation for new process, particularly use of a proxy. (2hrs 45mins)
5. Accounting - continue setting up new free accounting software. (1hr 20mins)

Friday, September 23, 2016

Today's work on/in the business - Thurs 22 September

1. Update my record of time worked. (5mins)
2. Review progress made this week. (10mins)
3. Investigate process for next version of software project for new customer - investigation for new process, particularly use of a proxy. (1hr 45mins)
4. Accounting - continue setting up new free accounting software. (3hrs 40mins)
5. Preparation for next tutorial. (2hrs 30mins)

Thursday, September 22, 2016

Today's work on/in the business - Wed 21 September

1. Update my record of time worked. (5mins)
2. Review progress made this week. (15mins)
3. Investigate process for next version of software project for new customer - investigation for new process, particularly use of a proxy. (3hrs)
4. First tutorial - including final preparation time. (2hrs 30mins)
5. Accounting - continue setting up new free accounting software. (55mins)

Wednesday, September 21, 2016

Today's work on/in the business - Tues 20 September

1. Update my record of time worked. (5mins)
2. Review progress made this week. (5mins)
3. Investigate process for next version of software project for new customer - investigation for new process, particularly use of a proxy. (3hrs 5mins)
4. Call and preparation for first tutorial. (4hrs 25mins)
5. Accounting - continue setting up new free accounting software. (35mins)

Tuesday, September 20, 2016

Today's work on/in the business - Mon 19 September

1. Update my record of time worked. (5mins)
2. Review progress made last week and ensure the schedule is right for this week. (15mins)
3. Review the project schedules, adjusted all projects based on actual progress and added a week to software schedules. (5mins)
4. Backup mail locally. (10mins)
5. Investigate process for next version of software project for new customer - investigation for new process, particularly use of a proxy. (2hrs 55mins)
6. Accounting - continue setting up new free accounting software. (4hrs)

Monday, September 19, 2016

Today's work on/in the business - Sun 18 September

1. Update my record of time worked. (20mins)
2. Review progress made this week. (45mins)
3. Accounting - continue setting up new free accounting software. (3hrs 15mins)

Sunday, September 18, 2016

Today's work on/in the business - Sat 17 September

No recorded time today, but follow up to the internet issues of yesterday.

As the ISP wanted the router to be reset to factory defaults yesterday, I recorded all details I could find from the current setup, then reset the router to factory defaults about 10.35am, while Dave was out working. Sadly, even this did not give internet access (even before any changes were made). So I did a small amount of setup for our local network, then waited for the call back from the ISP that I had booked late yesterday.

Call back did not happen as expected between 1pm and 2.45pm (booked for 2pm), so I rebooked it for 3pm. About 3.15pm we got the call... Sadly, not all the information I included in the two call back request details got to the woman who called, but she worked with Dave and I to fix it. We had to use a different router (again!!!!), but with a lot of work, we got a connection to the ISP, then with a bit more setup we actually got a real internet connection again! Full credit to the woman who stuck with us and assisted in resolving the issue - but sad that this is the second time one of their outages has meant that we have to totally rebuild our router setup!

Today's work on/in the business - Fri 16 September

1. Review progress made this week. (10mins)
2. Accounting - continue setting up new free accounting software. (4hrs 15mins)
3. Top up mobile broadband (because we have no internet...). (25mins)
4. Update my record of time worked. (5mins)

Much more time than this spent - we woke to no internet connection, but Dave was already committed to other work. So I did the reboot of everything, then called our ISP. About an hour and a half later, I spoke to someone who did tests and informed me that it was all good, as she could see us connected and traffic happening. Used mobile broadband to do a bit more investigation, then powered off router for 15mins and restarted - still no joy. Called ISP again, to get basically the same result - yes, you are connected, no I have no evidence of that from this end. Totally frustrating - then Dave came back and he did some investigation as well, with no results.

Friday, September 16, 2016

Today's work on/in the business - Thurs 15 September

1. Update my record of time worked. (5mins)
2. Review progress made this week. (15mins)
3. Accounting - continue setting up new free accounting software. (4hrs 10mins)
4. Investigate process for next version of software project for new customer - investigation for new process, particularly use of a proxy. (4hrs 55mins)

Thursday, September 15, 2016

Today's work on/in the business - Wed 14 September

1. Update my record of time worked. (5mins)
2. Review progress made this week. (15mins)
3. Investigate process for next version of software project for new customer - investigation for new process, particularly use of a proxy. (4hrs 40mins)
4. Accounting - continue setting up new free accounting software. (3hrs 45mins)

Wednesday, September 14, 2016

Today's work on/in the business - Tues 13 September

1. Update my record of time worked. (5mins)
2. Review progress made this week. (5mins)
3. Investigate process for next version of software project for new customer - investigation for new process, particularly use of a proxy. (6hrs 10mins)
4. Working on process for new Events setup - review events. (10mins)
5. Accounting - continue setting up new free accounting software. (1hr 15mins)

Tuesday, September 13, 2016

Today's work on/in the business - Mon 12 September

1. Update my record of time worked. (10mins)
2. Review progress made last week and ensure the schedule is right for this week. (35mins)
3. Review the project schedules, adjusted all projects based on actual progress and added a week to software schedules. (5mins)
4. Backup mail locally. (15mins)
5. Investigate process for next version of software project for new customer - investigation for new process, particularly use of a proxy. (7hrs 20mins)
6. Accounting - continue setting up new free accounting software. (1hr 50mins)

Monday, September 12, 2016

Today's work on/in the business - Sun 11 September

1. Accounting - continue setting up new free accounting software. (3hrs 45mins)

Today's work on/in the business - Sat 10 September

1. Accounting - continue setting up new free accounting software. (3hrs 20mins)

Today's work on/in the business - Fri 9 September

1. Update my record of time worked. (5mins)
2. Review progress made this week. (15mins)
3. Working on process for new Events setup - review events. (5mins)
4. Accounting - continue setting up new free accounting software. (2hrs 5mins)
5. Investigate process for next version of software project for new customer - investigation for new process, particularly use of a proxy. (6hrs 20mins)

Friday, September 9, 2016

Today's work on/in the business - Thurs 8 September

1. Update my record of time worked. (5mins)
2. Review progress made this week. (25mins)
3. Investigate process for next version of software project for new customer - investigation for new process, particularly use of a proxy. (7hrs)
4. Accounting - continue setting up new free accounting software. (30mins)

Thursday, September 8, 2016

Today's work on/in the business - Wed 7 September

1. Update my record of time worked. (5mins)
2. Review progress made this week. (10mins)
3. Investigate process for next version of software project for new customer - investigation for new process, particularly use of a proxy. (1hr 35mins)
4. Accounting - continue setting up new free accounting software. (1hr 55mins)

Too much time spent getting car parts, sorting out paperwork for other job and shopping!

Wednesday, September 7, 2016

Today's work on/in the business - Tues 6 September

1. Update my record of time worked. (5mins)
2. Review progress made this week. (15mins)
3. Top up mobile phone. (5mins)
4. Review the project schedules, adjusted all projects based on actual progress and added a week to software schedules. (5mins)
5. Backup mail locally. (20mins)
6. Investigate process for next version of software project for new customer - investigation for new process, particularly use of a proxy. (7hrs 55mins)

Tuesday, September 6, 2016

Today's work on/in the business - Mon 5 September

1. Update my record of time worked. (10mins)
2. Review progress made last week and ensure the schedule is right for this week. (15mins)
3. Investigate process for next version of software project for new customer - investigation for new process, particularly use of a proxy. (3hrs)
4. Accounting - continue setting up new free accounting software. (3hrs 35mins)

Monday, September 5, 2016

Today's work on/in the business - Sun 4 September

1. Accounting - continue setting up new free accounting software. (4hrs 15mins)

Today's work on/in the business - Sat 3 September

1. Accounting - continue setting up new free accounting software. (8hrs 15mins)

Today's work on/in the business - Fri 2 September

1. Update my record of time worked. (5mins)
2. Review progress made this week. (15mins)
3. Working on process for new Events setup - review events. (25mins)
4. Accounting - continue setting up new free accounting software. (6hrs 50mins)

Friday, September 2, 2016

Today's work on/in the business - Thurs 1 September

SPRING!!!!!

1. Update my record of time worked. (15mins)
2. Review progress made this week. (25mins)
3. Investigate process for next version of software project for new customer - investigation for new process, particularly use of a proxy. (2hrs 45mins)
4. Accounting - continue setting up new free accounting software. (5hrs 25mins)

Thursday, September 1, 2016

Today's work on/in the business - Wed 31 August

1. Update my record of time worked. (10mins)
2. Review progress made this week. (15mins)
3. Investigate process for next version of software project for new customer - investigation for new process, particularly use of a proxy. (2hrs 35mins)
4. Accounting - continue setting up new free accounting software. (2hrs 20mins)

Plus time running around in preparation then the orientation meeting in the evening for tutoring work.

Wednesday, August 31, 2016

Today's work on/in the business - Tues 30 August

1. Update my record of time worked. (10mins)
2. Investigate process for next version of software project for new customer - investigation for new process, particularly use of a proxy. (3hrs 25mins)
3. Review progress made this week. (10mins)
4. Working on process for new Events setup - review events. (25mins)
5. Accounting - continue setting up new free accounting software. (2hrs 35mins)

Tuesday, August 30, 2016

Today's work on/in the business - Mon 29 August

1. Update my record of time worked. (15mins)
2. Review progress made last week and ensure the schedule is right for this week. (20mins)
3. Review the project schedules, adjusted all projects based on actual progress and added a week to software schedules. (5mins)
4. Backup mail locally. (15mins)
5. Investigate process for next version of software project for new customer - investigation for new process, particularly use of a proxy. (2hrs 10mins)
6. Working on process for new Events setup - review events and enter regular events. (1hr 20mins)
7. Accounting - continue setting up new free accounting software. (5hrs)

Monday, August 29, 2016

Today's work on/in the business - Sat 27 August

1. Accounting - continue setting up new free accounting software. (35mins)

Today's work on/in the business - Fri 26 August

1. Update my record of time worked. (5mins)
2. Review progress made this week. (15mins)
3. Investigate process for next version of software project for new customer - investigation for new process, particularly use of a proxy. (1hr 45mins)
4. Accounting - continue setting up new free accounting software. (6hrs 10mins)

Friday, August 26, 2016

Today's work on/in the business - Thurs 25 August

1. Update my record of time worked. (5mins)
2. Review progress made this week. (10mins)
3. Investigate process for next version of software project for new customer - investigation for new process, particularly use of a proxy. (5hrs 5mins)
4. Accounting - continue setting up new free accounting software. (2hrs 50mins)

Thursday, August 25, 2016

Today's work on/in the business - Wed 24 August

1. Update my record of time worked. (5mins)
2. Review progress made this week. (10mins)
3. Investigate process for next version of software project for new customer - investigation for new process, particularly use of a proxy. (6hrs 15mins)
4. Accounting - continue setting up new free accounting software. (2hrs 15mins)

Wednesday, August 24, 2016

Today's work on/in the business - Tues 23 August

1. Update my record of time worked. (5mins)
2. Review progress made this week. (10mins)
3. Investigate process for next version of software project for new customer - investigation for new process, particularly use of a proxy. (1hr 55mins)
4. Accounting - continue setting up new free accounting software. (5hrs 35mins)

Tuesday, August 23, 2016

Today's work on/in the business - Mon 22 August

1. Update my record of time worked. (5mins)
2. Review progress made last week and ensure the schedule is right for this week. (20mins)
3. Review the project schedules, adjusted all projects based on actual progress and added a week to software schedules. (5mins)
4. Backup mail locally. (30mins)
5. Investigate process for next version of software project for new customer - investigation for new process, particularly use of a proxy. (2hrs 20mins)
6. Accounting - continue setting up new free accounting software. (6hrs 15mins)

Monday, August 22, 2016

Today's work on/in the business - Fri 19 August

1. Update my record of time worked. (5mins)
2. Review progress made this week. (10mins)
3. Working on process for new Events setup - review events. (5mins)
4. Investigate process for next version of software project for new customer - investigation for new process, particularly use of a proxy. (3hrs 50mins)
5. Accounting - continue setting up new free accounting software. (4hrs 10mins)

Friday, August 19, 2016

Today's work on/in the business - Thurs 18 August

1. Update my record of time worked. (5mins)
2. Review progress made this week. (10mins)
3. Investigate process for next version of software project for new customer - investigation for new process, particularly use of a proxy. (5hrs 40mins)
4. Top up mobile phone. (5mins)
5. Accounting - continue setting up new free accounting software. (3hrs 5mins)

Thursday, August 18, 2016

Today's work on/in the business - Wed 17 August

1. Update my record of time worked. (5mins)
2. Review progress made this week. (10mins)
3. Accounting - continue setting up new free accounting software. (1hr 50mins)
4. Investigate process for next version of software project for new customer - investigation for new process, particularly use of a proxy. (3hrs 15mins)

Wednesday, August 17, 2016

Today's work on/in the business - Tues 16 August

1. Update my record of time worked. (45mins)
2. Investigate process for next version of software project for new customer - investigation for new process, particularly use of a proxy. (3hrs 25mins)
3. Review progress made this week. (40mins)
4. Accounting - continue setting up new free accounting software. (2hrs 45mins)

Tuesday, August 16, 2016

Today's work on/in the business - Mon 15 August

1. Update my record of time worked. (5mins)
2. Review progress made last week and ensure the schedule is right for this week. (20mins)
3. Review the project schedules, adjusted all projects based on actual progress and added a week to software schedules. (5mins)
4. Backup mail locally. (10mins)
5. Accounting - continue setting up new free accounting software. (3hrs 25mins)
6. Investigate process for next version of software project for new customer - investigation for new process, particularly use of a proxy. (3hrs 5mins)

Monday, August 15, 2016

Today's work on/in the business - Sun 14 August

1. Accounting - continue setting up new free accounting software. (11hrs 20mins)

Today's work on/in the business - Sat 13 August

1. Update my record of time worked. (10mins)
2. Review progress made this week. (5mins)
3. Accounting - continue setting up new free accounting software. (6hrs 50mins)

Saturday, August 13, 2016

Today's work on/in the business - Fri 12 August

1. Update my record of time worked. (5mins)
2. Review progress made this week. (10mins)
3. Investigate process for next version of software project for new customer - investigation for new process, particularly use of a proxy. (2hrs 55mins)
4. Accounting - find and start setting up new free accounting software. (4hrs 50mins)

Friday, August 12, 2016

Today's work on/in the business - Thurs 11 August

1. Update my record of time worked. (5mins)
2. Review progress made this week. (10mins)
3. Investigate process for next version of software project for new customer - investigation for new process, particularly use of a proxy. (7hrs 25mins)

Thursday, August 11, 2016

Today's work on/in the business - Wed 10 August

1. Update my record of time worked. (10mins)
2. Review progress made this week. (10mins)
3. Investigate process for next version of software project for new customer - investigation for new process, particularly use of a proxy. (2hrs 15mins)

Funerals are not conducive to a productive work day...

Wednesday, August 10, 2016

Today's work on/in the business - Tues 9 August

1. Update my record of time worked. (10mins)
2. Review progress made this week. (10mins)
3. Investigate process for next version of software project for new customer - investigation for new process, particularly use of a proxy. (6hrs 55mins)
4. Search for contract work. (25mins)

Tuesday, August 9, 2016

Today's work on/in the business - Mon 8 August

1. Update my record of time worked. (10mins)
2. Review progress made last week and ensure the schedule is right for this week. (30mins)
3. Review the project schedules, adjusted all projects based on actual progress and added a week to software schedules. (5mins)
4. Backup mail locally. (25mins)
5. Investigate process for next version of software project for new customer - investigation for new process, particularly use of a proxy. (7hrs 20mins)

Monday, August 8, 2016

Today's work on/in the business - Fri 5 August

1. Update my record of time worked. (5mins)
2. Review progress made this week. (20mins)
3. Investigate process for next version of software project for new customer - investigation for new process, particularly use of a proxy. (5hrs 55mins)
4. Search for contract work. (2hrs 55mins)

Friday, August 5, 2016

Today's work on/in the business - Thurs 4 August

1. Update my record of time worked. (15mins)
2. Review progress made this week. (20mins)
3. Investigate process for next version of software project for new customer - investigation for new process, particularly use of a proxy. (7hrs 50mins)

Thursday, August 4, 2016

Today's work on/in the business - Wed 3 August

1. Update my record of time worked. (5mins)
2. Review progress made this week. (10mins)
3. Search for contract work. (25mins)
4. Investigate process for next version of software project for new customer - investigation for new process, particularly use of a proxy. (6hrs)
5. Working on process for new Events setup - review events. (25mins)
6. Review system after moving it to another server. (2hrs 10mins)

Wednesday, August 3, 2016

Today's work on/in the business - Tues 2 August

1. Update my record of time worked. (10mins)
2. Review progress made this week. (15mins)
3. Investigate process for next version of software project for new customer - investigation for new process, particularly use of a proxy. (8hrs 15mins)

Tuesday, August 2, 2016

Today's work on/in the business - Mon 1 August

1. Update my record of time worked. (10mins)
2. Trying to fix issues with a major piece of software on HP laptop that I must have working. (2hrs 40mins)
3. Setup required software on new laptop after being unable to fix it on HP laptop. (1hr 5mins)
4. Review progress made last week and ensure the schedule is right for this week. (45mins)
5. Review the project schedules, adjusted all projects based on actual progress and added a week to software schedules. (5mins)
6. Backup mail locally. (10mins)
7. Working on process for new Events setup - review events. (15mins)

Monday, August 1, 2016

Today's work on/in the business - Sat 30 July

1. Update my record of time worked. (15mins)
2. Export accounting information in case we need to use it elsewhere, and prepare for tax returns. (7hrs 10mins)

Saturday, July 30, 2016

Today's work on/in the business - Fri 29 July

1. Backup files from new laptop to NAS in preparation for upgrade to Windows 10. (6hrs 40mins)
2. Upgrade new laptop to Windows 10. (1hr 45mins)
3. Update my record of time worked. (15mins)
4. Review progress made this week. (15mins)
5. Investigate process for next version of software project for new customer - investigation for new process, particularly use of a proxy. (2hrs 15mins)
6. Run updates on HP laptop after power was lost but it did not shut down correctly - still issues with a major piece of software that I must have working. (4hrs 45mins)

Friday, July 29, 2016

Today's work on/in the business - Thurs 28 July

1. Update my record of time worked. (10mins)
2. Review progress made this week. (15mins)
3. Working on process for new Events setup - review events. (10mins)
4. Investigate process for next version of software project for new customer - investigation for new process, particularly use of a proxy. (2hrs 10mins)
5. Accounting. (3hrs 20mins)
6. Work on a different website for a branch of our business - trying to track down items in the new template that need changing. (1hr 55mins)
7. Backup files from new laptop to NAS in preparation for upgrade to Windows 10. (3hrs 35mins)

Thursday, July 28, 2016

Today's work on/in the business - Wed 27 July

1. Update my record of time worked. (5mins)
2. Run anti-virus on laptops. (40mins)
3. Review progress made this week. (15mins)
4. Review and respond to email from customer re moving system to another server. (15mins)
5. Accounting. (4hrs 20mins)
6. Working on process for new Events setup - review events and enter regular events. (2hrs 20mins)

Wednesday, July 27, 2016

Today's work on/in the business - Tues 26 July

1. Update my record of time worked. (10mins)
2. Review progress made this week. (15mins)
3. Investigate process for next version of software project for new customer - investigation for new process, particularly use of a proxy. (5hrs 15mins)
4. Accounting. (3hrs 55mins)

Tuesday, July 26, 2016

Today's work on/in the business - Mon 25 July

1. Update my record of time worked. (5mins)
2. Run anti-virus on laptops. (2hrs 45mins)
3. Review progress made last week and ensure the schedule is right for this week. (45mins)
4. Review the project schedules, adjusted all projects based on actual progress and added a week to software schedules. (5mins)
5. Backup mail locally. (20mins)
6. Investigate process for next version of software project for new customer - investigation for new process, particularly use of a proxy. (5hrs 55mins)

Monday, July 25, 2016

Today's work on/in the business - Fri 22 July

1. Update my record of time worked. (5mins)
2. Review progress made this week. (10mins)
3. Search for contract work. (1hr 55mins)
4. Investigate process for next version of software project for new customer - investigation for new process, particularly use of a proxy. (6hrs 15mins)
5. Run anti-virus on laptops. (3hrs)

Friday, July 22, 2016

Today's work on/in the business - Thurs 21 July

1. Update my record of time worked. (10mins)
2. Review progress made this week. (10mins)
3. Investigate process for next version of software project for new customer - investigation for new process, particularly use of a proxy. (6hrs 50mins)
4. Run anti-virus on laptops. (2hrs 35mins)

Thursday, July 21, 2016

Today's work on/in the business - Wed 20 July

1. Update my record of time worked. (5mins)
2. Review progress made this week. (10mins)
3. Investigate process for next version of software project for new customer - investigation for new process, particularly use of a proxy. (6hrs 55mins)
4. Run anti-virus on laptops. (3hrs)

Wednesday, July 20, 2016

Today's work on/in the business - Tues 19 July

1. Update my record of time worked. (5mins)
2. Review progress made this week. (10mins)
3. Investigate process for next version of software project for new customer - investigation for new process, particularly use of a proxy. (5hrs 20mins)
4. Run anti-virus on laptops. (6hrs10mins)

Tuesday, July 19, 2016

Today's work on/in the business - Mon 18 July

1. Update my record of time worked. (5mins)
2. Review progress made last week and ensure the schedule is right for this week. (20mins)
3. Review the project schedules, adjusted all projects based on actual progress and added a week to software schedules. (5mins)
4. Backup mail locally. (30mins)
5. Run anti-virus on laptops. (9hrs)

Blergh... upset stomach overnight... no energy or concentration to do any real work.

Monday, July 18, 2016

Today's work on/in the business - Sun 17 July

1. Investigate process for next version of software project for new customer - investigation for new process, particularly use of a proxy. (50mins)

Today's work on/in the business - Fri 15 July

1. Update my record of time worked. (5mins)
2. Review progress made this week. (10mins)
3. Investigate process for next version of software project for new customer - investigation for new process, particularly use of a proxy. (6hrs 5mins)

Friday, July 15, 2016

Today's work on/in the business - Thurs 14 July

1. Update my record of time worked. (5mins)
2. Review progress made this week. (10mins)
3. Investigate process for next version of software project for new customer - investigation for new process, particularly use of a proxy. (8hrs 35mins)

Thursday, July 14, 2016

Today's work on/in the business - Wed 13 July

1. Update my record of time worked. (5mins)
2. Review progress made this week. (10mins)
3. Investigate process for next version of software project for new customer - investigation for new process, particularly use of a proxy. (7hrs 10mins)

Wednesday, July 13, 2016

Today's work on/in the business - Tues 12 July

1. Update my record of time worked. (5mins)
2. Review progress made this week. (5mins)
3. Working on process for new Events setup - review events. (10mins)
4. Investigate process for next version of software project for new customer - investigation for new process, particularly use of a proxy. (7hrs 15mins)

Tuesday, July 12, 2016

Today's work on/in the business - Mon 11 July

1. Update my record of time worked. (5mins)
2. Review progress made last week and ensure the schedule is right for this week. (15mins)
3. Backup mail locally. (10mins)
4. Review the project schedules, adjusted all projects based on actual progress and added a week to software schedules. (5mins)
5. Investigate process for next version of software project for new customer - investigation for new process, particularly use of a proxy. (7hrs 5mins)

Monday, July 11, 2016

Today's work on/in the business - Thurs 7 July

1. Update my record of time worked. (10mins)
2. Review progress made this week. (20mins)

I tried to do more work, but I had to shop and pack as preparation for our weekend away - for us as well as the other blokes... (but that's another blog post!)

Now, we are back - and normal life starts again... for a while at least. :)

Thursday, July 7, 2016

Today's work on/in the business - Wed 6 July

1. Update my record of time worked. (10mins)
2. Review progress made this week. (10mins)
3. Working on process for new Events setup - review events. (1hr 5mins)
4. Investigate process for next version of software project for new customer - investigation for new process, particularly use of a proxy. (6hrs 25mins)
5. Work on a different website for a branch of our business - trying to track down items in the next new template that need changing. (15mins)

Wednesday, July 6, 2016

Today's work on/in the business - Tues 5 July

1. Update my record of time worked. (5mins)
2. Review progress made this week. (10mins)
3. Working on process for new Events setup - review events. (25mins)
4. Investigate process for next version of software project for new customer - investigation for new process, particularly use of a proxy. (8hrs 35mins)
5. Work on a different website for a branch of our business - trying to track down items in the new template that need changing. (2hrs 20mins)

Tuesday, July 5, 2016

Today's work on/in the business - Mon 4 July

1. Update my record of time worked. (5mins)
2. Review progress made last week and ensure the schedule is right for this week. (20mins)
3. Review the project schedules, adjusted all projects based on actual progress and added a week to software schedules. (5mins)
4. Backup mail locally. (25mins)
5. Investigate process for next version of software project for new customer - investigation for new process, particularly use of a proxy. (7hrs 35mins)

Monday, July 4, 2016

Today's work on/in the business - Fri 1 July

1. Update my record of time worked. (5mins)
2. Review progress made this week. (10mins)
3. Search for contract work. (30mins)
4. Investigate process for next version of software project for new customer - investigation for new process, particularly use of a proxy. (10hrs 5mins)

Friday, July 1, 2016

Today's work on/in the business - Thurs 30 June

1. Update my record of time worked. (5mins)
2. Review progress made this week. (20mins)
3. Investigate process for next version of software project for new customer - investigation for new process, particularly use of a proxy. (7hrs 5mins)

Thursday, June 30, 2016

Today's work on/in the business - Wed 29 June

1. Update my record of time worked. (5mins)
2. Review progress made this week. (30mins)
3. Working on process for new Events setup - review events and enter regular events. (1hr 35mins)
4. Investigate process for next version of software project for new customer - investigation for new process, particularly use of a proxy. (6hrs 40mins)

Wednesday, June 29, 2016

Today's work on/in the business - Tues 28 June

1. Update my record of time worked. (5mins)
2. Review progress made this week. (10mins)
3. Investigate process for next version of software project for new customer - investigation for new process, particularly use of a proxy. (7hrs 25mins)
4. Invoice reconciliation - talk to one customer and send out email. (25mins)

Tuesday, June 28, 2016

Today's work on/in the business - Mon 27 June

1. Update my record of time worked. (5mins)
2. Review progress made last week and ensure the schedule is right for this week. (20mins)
3. Review the project schedules, adjusted all projects based on actual progress and added a week to software schedules. (5mins)
4. Backup mail locally - both laptops. (30mins)
5. Invoice reconciliation - find one email address, update one invoice, send out invoices to two customers. (20mins)
6. Investigate process for next version of software project for new customer - investigation for new process, particularly use of a proxy. (6hrs 15mins)

Monday, June 27, 2016

Today's work on/in the business - Fri 24 June

1. Update my record of time worked. (5mins)
2. Review progress made this week. (10mins)
3. Investigate process for next version of software project for new customer - investigation for new process, particularly use of a proxy. (9hrs 40mins)

Friday, June 24, 2016

Today's work on/in the business - Thurs 23 June

1. Update my record of time worked. (5mins)
2. Review progress made this week. (5mins)
3. Investigate process for next version of software project for new customer - investigation for new process, particularly use of a proxy. (8hrs)

Thursday, June 23, 2016

Today's work on/in the business - Wed 22 June

1. Update my record of time worked. (5mins)
2. Review progress made this week. (5mins)
3. Investigate process for next version of software project for new customer - investigation for new process, particularly use of a proxy. (8hrs 35mins)

Wednesday, June 22, 2016

Today's work on/in the business - Tues 21 June

1. Update my record of time worked. (5mins)
2. Review progress made this week. (5mins)
3. Investigate process for next version of software project for new customer - investigation for new process, particularly use of a proxy. (9hrs 30mins)

Tuesday, June 21, 2016

Today's work on/in the business - Mon 20 June

1. Update my record of time worked. (5mins)
2. Review progress made last week and ensure the schedule is right for this week. (10mins)
3. Review the project schedules, adjusted all projects based on actual progress and added a week to software schedules. (5mins)
4. Backup mail locally. (10mins)
5. Investigate process for next version of software project for new customer - investigation for new process, particularly use of a proxy. (7hrs 35mins)

Monday, June 20, 2016

Today's work on/in the business - Fri 17 June

1. Update my record of time worked. (10mins)
2. Review progress made this week. (10mins)
3. Top up mobile broadband. (5mins)
4. Investigate process for next version of software project for new customer - investigation for new process, particularly use of a proxy. (8hrs 55mins)

Friday, June 17, 2016

Today's work on/in the business - Thurs 16 June

1. Investigate process for next version of software project for new customer - investigation for new process, particularly use of a proxy. (6hrs 35mins)
2. Update my record of time worked. (10mins)
3. Review progress made this week. (10mins)
4. Working on process for new Events setup - review events. (5mins)

Thursday, June 16, 2016

Today's work on/in the business - Wed 15 June

1. Investigate process for next version of software project for new customer - investigation for new process, particularly use of a proxy. (8hrs 40mins)
2. Update my record of time worked. (10mins)
3. Review progress made this week. (10mins)

Wednesday, June 15, 2016

Today's work on/in the business - Tues 14 June

1. Update my record of time worked. (5mins)
2. Review progress made this week. (5mins)
3. Working on process for new Events setup - review events. (20mins)
4. Investigate process for next version of software project for new customer - investigation for new process, particularly use of a proxy. (3hrs 40mins)

Tuesday, June 14, 2016

Today's work on/in the business - Mon 13 June

1. Update my record of time worked. (5mins)
2. Review progress made last week and ensure the schedule is right for this week. (20mins)
3. Review the project schedules, adjusted all projects based on actual progress and added a week to software schedules. (5mins)
4. Backup mail locally. (5mins)
5. Accounting - bring recording up to date. (1hr 35mins)

Monday, June 13, 2016

Today's work on/in the business - Fri 10 June

1. Update my record of time worked. (10mins)
2. Review progress made this week. (10mins)
3. Investigate process for next version of software project for new customer - investigation for new process, particularly use of a proxy. (7hrs 15mins)
4. Work on our server - upgrade of Ubuntu broke a couple of things, which needed to be addressed as soon as possible. (2hrs 20mins)

Friday, June 10, 2016

Today's work on/in the business - Thurs 9 June

1. Update my record of time worked. (5mins)
2. Review progress made this week. (10mins)
3. Investigate process for next version of software project for new customer - investigation for new process, particularly use of a proxy. (7hrs 40mins)

Thursday, June 9, 2016

Today's work on/in the business - Wed 8 June

1. Update my record of time worked. (5mins)
2. Review progress made this week. (5mins)
3. Investigate process for next version of software project for new customer - investigation for new process, particularly use of a proxy. (7hrs 45mins)

Wednesday, June 8, 2016

Today's work on/in the business - Tues 7 June

1. Update my record of time worked. (5mins)
2. Investigate process for next version of software project for new customer - investigation for new process, particularly use of a proxy. (12hrs 15mins)
3. Review progress made this week. (15mins)

Tuesday, June 7, 2016

Today's work on/in the business - Mon 6 June

1. Update my record of time worked. (5mins)
2. Review progress made last week and ensure the schedule is right for this week. (15mins)
3. Review the project schedules, adjusted all projects based on actual progress and added a week to software schedules. (5mins)
4. Backup mail locally. (10mins)
5. Investigate process for next version of software project for new customer - investigation for new process, particularly use of a proxy. (7hrs 20mins)

Monday, June 6, 2016

Today's work on/in the business - Fri 3 June

1. Investigate process for next version of software project for new customer - investigation for new process, particularly use of a proxy. (7hrs 20mins)
2. Update my record of time worked. (5mins)
3. Review progress made this week. (5mins)

Friday, June 3, 2016

Today's work on/in the business - Thurs 2 June

1. Update my record of time worked. (10mins)
2. Review progress made this week. (15mins)
3. Investigate process for next version of software project for new customer - investigation for new process, particularly use of a proxy. (8hrs 50mins)

Thursday, June 2, 2016

Today's work on/in the business - Wed 1 June

1. Update my record of time worked. (10mins)
2. Review progress made this week. (10mins)
3. Working on process for new Events setup - review events. (25mins)
4. Investigate process for next version of software project for new customer - investigation for new process, particularly use of a proxy. (7hrs 45mins)

Wednesday, June 1, 2016

Today's work on/in the business - Tues 31 May

1. Update my record of time worked. (10mins)
2. Review progress made this week. (10mins)
3. Working on process for new Events setup - review events. (25mins)
4. Investigate process for next version of software project for new customer - investigation for new process, particularly use of a proxy. (11hrs 15mins)

Tuesday, May 31, 2016

Today's work on/in the business - Mon 30 May

1. Update my record of time worked. (10mins)
2. Review progress made last week and ensure the schedule is right for this week. (25mins)
3. Investigate process for next version of software project for new customer - investigation for new process, particularly use of a proxy. (9hrs)
4. Review the project schedules, adjusted all projects based on actual progress and added a week to software schedules. (5mins)
5. Backup mail locally. (10mins)

Monday, May 30, 2016

Today's work on/in the business - Fri 27 May

1. Update my record of time worked. (10mins)
2. Review progress made this week. (5mins)
3. Working on process for new Events setup - review events and enter regular events. (2hrs 20mins)
4. Investigate process for next version of software project for new customer - investigation for new process, particularly use of a proxy. (2hrs 15mins)

Friday, May 27, 2016

Today's work on/in the business - Thurs 26 May

1. Investigate process for next version of software project for new customer - investigation for new process, particularly use of a proxy. (11hrs 25mins)
2. Update my record of time worked. (10mins)
3. Review progress made this week. (10mins)

Thursday, May 26, 2016

Today's work on/in the business - Wed 25 May

1. Update my record of time worked. (5mins)
2. Review progress made this week. (5mins)
3. Investigate process for next version of software project for new customer - investigation for new process, particularly use of a proxy. (5hrs)
4. Update resume and apply for contract work. (2hrs 45mins)

Wednesday, May 25, 2016

Today's work on/in the business - Tues 24 May

1. Update my record of time worked. (5mins)
2. Review progress made this week. (5mins)
3. Investigate process for next version of software project for new customer - investigation for new process, particularly use of a proxy. (9hrs 40mins)

Tuesday, May 24, 2016

Today's work on/in the business - Mon 23 May

1. Update my record of time worked. (5mins)
2. Review progress made last week and ensure the schedule is right for this week. (20mins)
3. Backup mail locally. (10mins)
4. Review the project schedules, adjusted all projects based on actual progress and added a week to software schedules. (5mins)
5. Investigate process for next version of software project for new customer - investigation for new process, particularly use of a proxy. (7hrs 55mins)

Monday, May 23, 2016

Today's work on/in the business - Fri 20 May

1. Update my record of time worked. (5mins)
2. Review progress made this week. (5mins)
3. Investigate process for next version of software project for new customer - investigation for new process, particularly use of a proxy. (7hrs 25mins)

Friday, May 20, 2016

Today's work on/in the business - Thurs 19 May

1. Update my record of time worked. (5mins)
2. Review progress made this week. (15mins)
3. Investigate process for next version of software project for new customer - investigation for new process, particularly use of a proxy. (8hrs 10mins)

Thursday, May 19, 2016

Today's work on/in the business - Wed 18 May

1. Update my record of time worked. (10mins)
2. Review progress made this week. (10mins)
3. Investigate process for next version of software project for new customer - investigation for new process, particularly use of a proxy. (2hrs 30mins)

Wednesday, May 18, 2016

Today's work on/in the business - Tues 17 May

1. Update my record of time worked. (10mins)
2. Review progress made this week. (10mins)
3. Investigate process for next version of software project for new customer - investigation for new process, particularly use of a proxy. (8hrs 20mins)

Tuesday, May 17, 2016

Today's work on/in the business - Mon 16 May

1. Update my record of time worked. (5mins)
2. Review progress made last week and ensure the schedule is right for this week. (10mins)
3. Review the project schedules, adjusted all projects based on actual progress and added a week to software schedules. (5mins)
4. Backup mail locally. (10mins)
5. Investigate process for next version of software project for new customer - investigation for new process, particularly use of a proxy. (7hrs 30mins)

Monday, May 16, 2016

Today's work on/in the business - Fri 13 May

1. Update my record of time worked. (5mins)
2. Review progress made this week. (5mins)
3. Investigate process for next version of software project for new customer - investigation for new process, particularly use of a proxy. (7hrs 50mins)
4. Invoice reconciliation - one more created. (5mins)

Friday, May 13, 2016

Today's work on/in the business - Thurs 12 May

1. Update my record of time worked. (5mins)
2. Review progress made this week. (20mins)
3. Investigate process for next version of software project for new customer - investigation for new process, particularly use of a proxy. (5hrs 10mins)
4. Invoice reconciliation - catching up on some of this. (2hrs 45mins)

Thursday, May 12, 2016

Today's work on/in the business - Wed 11 May

1. Update my record of time worked. (5mins)
2. Review progress made this week. (10mins)
3. Investigate process for next version of software project for new customer - investigation for new process, particularly use of a proxy. (7hrs 55mins)

Wednesday, May 11, 2016

Today's work on/in the business - Tues 10 May

1. Update my record of time worked. (5mins)
2. Review progress made this week. (10mins)
3. Investigate process for next version of software project for new customer - investigation for new process, particularly use of a proxy. (9hrs)

Tuesday, May 10, 2016

Today's work on/in the business - Mon 9 May

1. Update my record of time worked. (5mins)
2. Working on process for new Events setup - review events. (20mins)
3. Review progress made last week and ensure the schedule is right for this week. (20mins)
4. Review the project schedules, adjusted all projects based on actual progress and added a week to software schedules. (5mins)
5. Backup mail locally. (10mins)
6. Investigate process for next version of software project for new customer - investigation for new process, particularly use of a proxy. (8hrs 35mins)

Monday, May 9, 2016

Today's work on/in the business - Fri 6 May

1. Update my record of time worked. (5mins)
2. Review progress made this week. (10mins)
3. Working on process for new Events setup - review events. (20mins)
4. Investigate process for next version of software project for new customer - investigation for new process, particularly use of a proxy. (4hrs 20mins)
5. Accounting. (4hrs 10mins)

Friday, May 6, 2016

Today's work on/in the business - Thurs 5 May

1. Update my record of time worked. (5mins)
2. Review progress made this week. (5mins)
3. Investigate process for next version of software project for new customer - investigation for new process, particularly use of a proxy. (6hrs 45mins)

Thursday, May 5, 2016

Today's work on/in the business - Wed 4 May

1. Update my record of time worked. (5mins)
2. Review progress made this week. (5mins)
3. Investigate process for next version of software project for new customer - investigation for new process, particularly use of a proxy. (6hrs 45mins)

Wednesday, May 4, 2016

Today's work on/in the business - Tues 3 May

1. Update my record of time worked. (5mins)
2. Review progress made this week. (10mins)
3. Investigate process for next version of software project for new customer - investigation for new process, particularly use of a proxy. (9hrs 40mins)

Tuesday, May 3, 2016

Today's work on/in the business - Mon 2 May

1. Update my record of time worked. (10mins)
2. Review progress made last week and ensure the schedule is right for this week. (15mins)
3. Review the project schedules, adjusted all projects based on actual progress and added a week to software schedules. (5mins)
4. Backup mail locally. (10mins)
5. Investigate process for next version of software project for new customer - investigation for new process, particularly use of a proxy. (7hrs 5mins)
6. Working on process for new Events setup - review events and enter regular events. (1hr 30mins)

Monday, May 2, 2016

Today's work on/in the business - Fri 29 April

1. Update my record of time worked. (5mins)
2. Review progress made this week. (10mins)
3. Investigate process for next version of software project for new customer - investigation for new process, particularly use of a proxy. (8hrs 20mins)
4. Testing after upgrade to our main server. Some errors in the other server's mail log - that went away after the virus scan finished. (20mins)

Friday, April 29, 2016

Today's work on/in the business - Thurs 28 April

1. Update my record of time worked. (5mins)
2. Review progress made this week. (5mins)
3. Investigate process for next version of software project for new customer - investigation for new process, particularly use of a proxy. (5hrs 55mins)

Thursday, April 28, 2016

Today's work on/in the business - Wed 27 April

1. Update my record of time worked. (5mins)
2. Review progress made this week. (5mins)
3. Investigate process for next version of software project for new customer - investigation for new process, particularly use of a proxy. (9hrs 25mins)

Wednesday, April 27, 2016

Today's work on/in the business - Tues 26 April

1. Update my record of time worked. (10mins)
2. Review progress made this week. (25mins)
3. Investigate process for next version of software project for new customer - investigation for new process, particularly use of a proxy. (8hrs 30mins)

Tuesday, April 26, 2016

Today's work on/in the business - Sat 23 April

1. Update my record of time worked. (5mins)
2. Review progress made this week and ensure the schedule is right for next week. (15mins)
3. Review the project schedules, adjusted all projects based on actual progress and added a week to software schedules. (5mins)
4. Backup mail locally. (15mins)
5. Investigate process for next version of software project for new customer - investigation for new process, particularly use of a proxy. (5hrs)

Saturday, April 23, 2016

Today's work on/in the business - Fri 22 April

1. Update my record of time worked. (5mins)
2. Review progress made this week. (10mins)
3. Working on process for new Events setup - review events. (35mins)
4. Investigate process for next version of software project for new customer - investigation for new process, particularly use of a proxy. (8hrs 35mins)

Friday, April 22, 2016

Today's work on/in the business - Thurs 21 April

1. Update my record of time worked. (5mins)
2. Review progress made this week. (15mins)
3. Investigate process for next version of software project for new customer - investigation for new process, particularly use of a proxy. (4hrs 15mins)

Thursday, April 21, 2016

Today's work on/in the business - Wed 20 April

1. Update my record of time worked. (5mins)
2. Review progress made this week. (10mins)
3. Investigate process for next version of software project for new customer - investigation for new process, particularly use of a proxy. (7hrs 45mins)

Wednesday, April 20, 2016

Today's work on/in the business - Tues 19 April

1. Update my record of time worked. (5mins)
2. Review progress made this week. (5mins)
3. Investigate process for next version of software project for new customer - investigation for new process, particularly use of a proxy. (10hrs 20mins)

Tuesday, April 19, 2016

Today's work on/in the business - Mon 18 April

1. Update my record of time worked. (10mins)
2. Review progress made this week. (5mins)
3. Investigate process for next version of software project for new customer - investigation for new process, particularly use of a proxy. (6hrs 25mins)

Monday, April 18, 2016

Today's work on/in the business - Sun 17 April

1. Update my record of time worked. (15mins)
2. Review progress made this week and ensure the schedule is right for next week. (20mins)
3. Review the project schedules, adjusted all projects based on actual progress and added a week to software schedules. (5mins)
4. Backup mail locally. (10mins)
5. Investigate process for next version of software project for new customer - investigation for new process, particularly use of a proxy. (3hrs 15mins)

Sunday, April 17, 2016

Today's work on/in the business - Fri 15 April

1. Update my record of time worked. (5mins)
2. Review progress made this week. (10mins)
3. Assisting with redirect to new server for support customer. (35mins)
4. Investigate process for next version of software project for new customer - investigation for new process, particularly use of a proxy. (7hrs 15mins)

Friday, April 15, 2016

Today's work on/in the business - Thurs 14 April

1. Working on process for new Events setup - review events. (10mins)
2. Update my record of time worked. (5mins)
3. Review progress made this week. (5mins)
4. Investigate process for next version of software project for new customer - investigation for new process, particularly use of a proxy. (5hrs 10mins)

Thursday, April 14, 2016

Today's work on/in the business - Wed 13 April

1. Update my record of time worked. (15mins)
2. Review progress made this week. (15mins)
3. Investigate process for next version of software project for new customer - investigation for new process, particularly use of a proxy. (9hrs 35mins)
4. Working on process for new Events setup - review events. (20mins)

Wednesday, April 13, 2016

Today's work on/in the business - Tues 12 April

1. Update my record of time worked. (5mins)
2. Review progress made this week. (15mins)
3. Investigate process for next version of software project for new customer - investigation for new process, particularly use of a proxy. (8hrs 15mins)
4. Invoice reconciliation. (1hr 10mins)

Tuesday, April 12, 2016

Today's work on/in the business - Mon 11 April

1. Update my record of time worked. (10mins)
2. Review progress made last week and ensure the schedule is right for this week. (20mins)
3. Review the project schedules, adjusted all projects based on actual progress and added a week to software schedules. (5mins)
4. Backup mail locally. (10mins)
5. Investigate process for next version of software project for new customer - investigation for new process, particularly use of a proxy. (10hrs 5mins)

Monday, April 11, 2016

Today's work on/in the business - Sun 10 April

1. Assisting with redirect to new server for support customer, running backups, including correspondence with customer re changes. (10hrs 30mins)

Today's work on/in the business - Sat 9 April

1. Assisting with redirect to new server for support customer, replacement of NAS and setting up and running backups. (10hrs 20mins)
2. Update my record of time worked. (5mins)
3. Review progress made this week. (10mins)
4. Investigate process for next version of software project for new customer - investigation for new process, particularly use of a proxy. (30mins)

Saturday, April 9, 2016

Today's work on/in the business - Fri 8 April

1. Update my record of time worked. (5mins)
2. Review progress made this week. (20mins)
3. Assisting with redirect to new server for support customer. (1hr 10mins)
4. Investigate process for next version of software project for new customer - investigation for new process, particularly use of a proxy. (9hrs 5mins)

Friday, April 8, 2016

Today's work on/in the business - Thurs 7 April

1. Update my record of time worked. (5mins)
2. Review progress made this week. (10mins)
3. Investigate process for next version of software project for new customer - investigation for new process, particularly use of a proxy. (6hrs)
4. Assisting with diagnosis and swapping over to new server for support customer. (1hr 5mins)

Thursday, April 7, 2016

Today's work on/in the business - Wed 6 April

1. Update my record of time worked. (5mins)
2. Review progress made this week. (10mins)
3. Investigate process for next version of software project for new customer - investigation for new process, particularly use of a proxy. (8hrs 50mins)

Wednesday, April 6, 2016

Today's work on/in the business - Tues 5 April

1. Update my record of time worked. (5mins)
2. Review progress made this week. (10mins)
3. Assisting with diagnosis and swapping over to new server for support customer. (10hrs 10mins)
4. Investigate process for next version of software project for new customer - investigation for new process, particularly use of a proxy. (15mins)

Tuesday, April 5, 2016

Today's work on/in the business - Mon 4 April

1. Update my record of time worked. (10mins)
2. Review progress made last week and ensure the schedule is right for this week. (15mins)
3. Review the project schedules, adjusted all projects based on actual progress and added a week to software schedules. (5mins)
4. Backup mail locally. (10mins)
5. Investigate process for next version of software project for new customer - investigation for new process, particularly use of a proxy. (9hrs 15mins)

Monday, April 4, 2016

Today's work on/in the business - Fri 1 April

1. Update my record of time worked. (10mins)
2. Review progress made this week. (5mins)
3. Working on process for new Events setup - review events. (15mins)
4. Investigate process for next version of software project for new customer - investigation for new process, particularly use of a proxy. (8hrs 10mins)

Friday, April 1, 2016

Today's work on/in the business - Thurs 31 March

1. Update my record of time worked. (5mins)
2. Review progress made this week. (10mins)
3. Investigate process for next version of software project for new customer - investigation for new process, particularly use of a proxy. (5hrs 20mins)

Thursday, March 31, 2016

Today's work on/in the business - Wed 30 March

1. Update my record of time worked. (10mins)
2. Review progress made this week. (10mins)
3. Investigate process for next version of software project for new customer - investigation for new process, particularly use of a proxy. (9hrs 10mins)

Wednesday, March 30, 2016

Today's work on/in the business - Tues 29 March

1. Update my record of time worked. (10mins)
2. Review progress made this week. (10mins)
3. Investigate process for next version of software project for new customer - investigation for new process, particularly use of a proxy. (6hrs 50mins)
4. NAS - took it back, they are going to get a replacement in then we will swap it over. (40mins)
5. Working on process for new Events setup - review events and enter regular events. (1hr 20mins)

Tuesday, March 29, 2016

Today's work on/in the business - Mon 28 March

1. Update my record of time worked. (5mins)
2. Review progress made last week and ensure the schedule is right for this week. (20mins)
3. Review the project schedules, adjusted all projects based on actual progress and added a week to software schedules. (5mins)
4. Backup mail locally. (15mins)

Monday, March 28, 2016

Today's work on/in the business - Sat 26 March

1. NAS - tried to take it back, but they are shut over Easter. (30mins)
2. Update my record of time worked. (5mins)
3. Review progress made this week. (10mins)
4. Investigate process for next version of software project for new customer - investigation for new process, particularly use of a proxy. (2hrs 20mins)

Saturday, March 26, 2016

Today's work on/in the business - Fri 25 March

1. Update my record of time worked. (5mins)
2. Review progress made this week. (5mins)
3. NAS - working on trying to get consistent access - it is losing passwords and refusing connections. (1hr 5mins)
4. Investigate process for next version of software project for new customer - investigation for new process, particularly use of a proxy. (5hrs 50mins)

Friday, March 25, 2016

Today's work on/in the business - Thurs 24 March

1. Update my record of time worked. (5mins)
2. Investigate process for next version of software project for new customer - investigation for new process, particularly use of a proxy. (4hrs 40mins)
3. Review progress made this week. (5mins)

Thursday, March 24, 2016

Today's work on/in the business - Wed 23 March

1. Update my record of time worked. (5mins)
2. Review progress made this week. (5mins)
3. Investigate process for next version of software project for new customer - investigation for new process, particularly use of a proxy. (12hrs 35mins)

Wednesday, March 23, 2016

Today's work on/in the business - Tues 22 March

1. Update my record of time worked. (5mins)
2. Review progress made this week. (5mins)
3. Investigate process for next version of software project for new customer - investigation for new process, particularly use of a proxy. (10hrs 35mins)

Tuesday, March 22, 2016

Today's work on/in the business - Mon 21 March

1. Update my record of time worked. (5mins)
2. Review progress made last week and ensure the schedule is right for this week. (15mins)
3. Review the project schedules, adjusted all projects based on actual progress and added a week to software schedules. (5mins)
4. Backup mail locally. (10mins)
5. Investigate process for next version of software project for new customer - investigation for new process, particularly use of a proxy. (7hrs 55mins)

Monday, March 21, 2016

Today's work on/in the business - Fri 18 March

1. Update my record of time worked. (5mins)
2. Review progress made this week. (10mins)
3. Investigate process for next version of software project for new customer - investigation for new process, particularly use of a proxy. (6hrs 35mins)

Friday, March 18, 2016

Today's work on/in the business - Thurs 17 March

1. Update my record of time worked. (5mins)
2. Review progress made this week. (10mins)
3. Investigate process for next version of software project for new customer - investigation for new process, particularly use of a proxy. (5hrs 10mins)

More work on rebuilding cycling skills this morning.

Thursday, March 17, 2016

Today's work on/in the business - Wed 16 March

1. Update my record of time worked. (5mins)
2. Review progress made this week. (15mins)
3. Investigate process for next version of software project for new customer - investigation for new process, particularly use of a proxy. (35mins)

Then off to visit Healesville Sanctuary with our friends who are out from the UK!

Wednesday, March 16, 2016

Today's work on/in the business - Tues 15 March

1. Update my record of time worked. (5mins)
2. Review progress made last week and ensure the schedule is right for this week. (20mins)
3. Review the project schedules, adjusted all projects based on actual progress and added a week to software schedules. (5mins)
4. Backup mail locally. (5mins)
5. Investigate process for next version of software project for new customer - investigation for new process, particularly use of a proxy. (11hrs 10mins)

Tuesday, March 15, 2016

Today's work on/in the business - Fri 11 March

1. Update my record of time worked. (5mins)
2. Review progress made this week. (5mins)
3. Investigate process for next version of software project for new customer - investigation for new process, particularly use of a proxy. (10hrs 10mins)

And then I had a REAL long weekend - motorcycles, bbq, friends from the UK - wonderful!

Friday, March 11, 2016

Today's work on/in the business - Thurs 10 March

1. Update my record of time worked. (5mins)
2. Review progress made this week. (10mins)
3. Investigate process for next version of software project for new customer - investigation for new process, particularly use of a proxy. (4hrs 50mins)

Fun out rebuilding the cycling skills in the morning, then shopping...

Thursday, March 10, 2016

Today's work on/in the business - Wed 9 March

1. Update my record of time worked. (5mins)
2. Review progress made this week. (5mins)
3. Investigate process for next version of software project for new customer - investigation for new process, particularly use of a proxy. (11hrs 30mins)
4. New project - call re possible security testing. (10mins)

Wednesday, March 9, 2016

Today's work on/in the business - Tues 8 March

1. New project - call re possible changes. (5mins)
2. Update my record of time worked. (5mins)
3. Review progress made this week. (10mins)
4. Investigate process for next version of software project for new customer - investigation for new process, particularly use of a proxy. (8hrs 40mins)

Tuesday, March 8, 2016

Today's work on/in the business - Mon 7 March

1. Update my record of time worked. (5mins)
2. Review progress made last week and ensure the schedule is right for this week. (15mins)
3. Review the project schedules, adjusted all projects based on actual progress and added a week to software schedules. (5mins)
4. Backup mail locally. (10mins)
5. Investigate process for next version of software project for new customer - investigation for new process, particularly use of a proxy. (6hrs 20mins)

Monday, March 7, 2016

Today's work on/in the business - Fri 4 March

1. Update my record of time worked. (5mins)
2. Review progress made this week. (10mins)

Then we went away for a wonderful weeking talking about and admiring motorcycles!

Back to find that the smoke alarm had gone off, the police had sent the fire brigade, the fire brigade knocked down the newly replaced small piece of fence at the side of the house - fortunately I had accidentally left the back door on the latch, not locked, so they didn't have to actually break into the house (!) - just to pull the battery out....!!

Friday, March 4, 2016

Today's work on/in the business - Thurs 3 March

1. Update my record of time worked. (5mins)
2. Review progress made this week. (15mins)
3. Working on process for new Events setup - investigate issue with website. (15mins)
4. Investigate process for next version of software project for new customer - investigation for new process, particularly use of a proxy. (5hrs 30mins)

Time spent helping with motorcycle made up the rest of the time.

Thursday, March 3, 2016

Today's work on/in the business - Wed 2 March

1. Update my record of time worked. (5mins)
2. Review progress made this week. (10mins)
3. Working on process for new Events setup - investigate issue with website. (1hr 45mins)
4. Investigate process for next version of software project for new customer - investigation for new process, particularly use of a proxy. (7hrs 55mins)

Wednesday, March 2, 2016

Today's work on/in the business - Tues 1 March

1. Update my record of time worked. (5mins)
2. Review progress made this week. (15mins)
3. Working on process for new Events setup - investigate issue with website. (6hrs 15mins)
4. Investigate process for next version of software project for new customer - investigation for new process, particularly use of a proxy. (50mins)

Tuesday, March 1, 2016

Today's work on/in the business - Mon 29 February

1. Update my record of time worked. (5mins)
2. Review progress made last week and ensure the schedule is right for this week. (25mins)
3. Review the project schedules, adjusted all projects based on actual progress and added a week to software schedules. (5mins)
4. Backup mail locally. (10mins)
5. Working on process for new Events setup - investigate issue with website. (10hrs 50mins)
6. Investigate process for next version of software project for new customer - investigation for new process, particularly use of a proxy. (10mins)

Monday, February 29, 2016

Today's work on/in the business - Fri 26 February

1. Update my record of time worked. (5mins)
2. Review progress made this week. (15mins)
3. Investigate process for next version of software project for new customer - investigation for new process, particularly use of a proxy. (7hrs 5mins)
4. Working on process for new Events setup - review events. (10mins)

Friday, February 26, 2016

Today's work on/in the business - Thurs 25 February

1. Update my record of time worked. (5mins)
2. Review progress made this week. (5mins)
3. Investigate process for next version of software project for new customer - investigation for new process, particularly use of a proxy. (8hrs 20mins)
4. Working on process for new Events setup - review events. (5mins)

Thursday, February 25, 2016

Today's work on/in the business - Wed 24 February

1. Update my record of time worked. (5mins)
2. Review progress made this week. (10mins)
3. Investigate process for next version of software project for new customer - investigation for new process, particularly use of a proxy. (7hrs 35mins)
4. Working on process for new Events setup - review events. (5mins)

Wednesday, February 24, 2016

Today's work on/in the business - Tues 23 February

1. Update my record of time worked. (5mins)
2. Review progress made this week. (10mins)
3. Investigate process for next version of software project for new customer - investigation for new process, particularly use of a proxy. (8hrs 35mins)

Tuesday, February 23, 2016

Today's work on/in the business - Mon 22 February

1. Update my record of time worked. (10mins)
2. Review progress made last week and ensure the schedule is right for this week. (35mins)
3. Review the project schedules, adjusted all projects based on actual progress and added a week to software schedules. (5mins)
4. Backup mail locally. (10mins)
5. Investigate process for next version of software project for new customer - investigation for new process, particularly use of a proxy. (6hrs 35mins)

Monday, February 22, 2016

Today's work on/in the business - Sun 21 February

1. Customer website not functioning - hosting provider advised it fixed, verified this and contacted customer. (30mins)

Today's work on/in the business - Sat 20 February

1. Customer website not functioning - trying to contact hosting provider and determine cause and fix. (3hrs 30mins)

Today's work on/in the business - Fri 19 February

1. Update my record of time worked. (5mins)
2. Review progress made this week. (15mins)
3. Investigate process for next version of software project for new customer - investigation for new process, particularly use of a proxy. (8hrs 10mins)

Friday, February 19, 2016

Today's work on/in the business - Thurs 18 February

1. Update my record of time worked. (5mins)
2. Review progress made this week. (5mins)
3. Investigate process for next version of software project for new customer - investigation for new process, particularly use of a proxy. (5hrs 35mins)

Thursday, February 18, 2016

Today's work on/in the business - Wed 17 February

1. Update my record of time worked. (10mins)
2. Review progress made this week. (10mins)
3. Investigate process for next version of software project for new customer - investigation for new process, particularly use of a proxy. (9hrs 15mins)

Wednesday, February 17, 2016

Today's work on/in the business - Tues 16 February

1. Update my record of time worked. (5mins)
2. Review progress made this week. (10mins)
3. Investigate process for next version of software project for new customer - investigation for new process, particularly use of a proxy. (9hrs 35mins)

Tuesday, February 16, 2016

Today's work on/in the business - Mon 15 February

1. Update my record of time worked. (5mins)
2. Review progress made this week. (5mins)
3. New project - working on last issue reported. (1hr 50mins)
4. Investigate process for next version of software project for new customer - investigation for new process, particularly use of a proxy. (7hrs 15mins)

Monday, February 15, 2016

Today's work on/in the business - Sat 13 February

1. Update my record of time worked. (5mins)
2. Review progress made this week and ensure the schedule is right for next week. (25mins)
3. Review the project schedules, adjusted all projects based on actual progress and added a week to software schedules. (5mins)
6. Backup mail locally. (10mins)

Saturday, February 13, 2016

Today's work on/in the business - Fri 12 February

1. Update my record of time worked. (5mins)
2. Review progress made this week. (10mins)
3. Working on process for new Events setup - review events. (15mins)
4. Investigate process for next version of software project for new customer - investigation for new process, particularly use of a proxy. (1hr 40mins)
5. Accounting - continue entering. (3hrs 20mins)
6. Invoice reconciliation - complete and send one invoice, updating other records. (2hrs)

Friday, February 12, 2016

Today's work on/in the business - Thurs 11 February

1. Update my record of time worked. (5mins)
2. Review progress made this week. (10mins)
3. Accounting - start entering. (7hrs 25mins)
4. Investigate process for next version of software project for new customer - investigation for new process, particularly use of a proxy. (1hr 15mins)

Thursday, February 11, 2016

Today's work on/in the business - Wed 10 February

1. Update my record of time worked. (5mins)
2. Review progress made this week. (10mins)
3. Accounting - sort paperwork, ready to enter. (4hrs 10mins)

Wednesday, February 10, 2016

Today's work on/in the business - Tues 9 February

1. Update my record of time worked. (5mins)
2. Review progress made last week and ensure the schedule is right for this week. (20mins)
3. Working on process for new Events setup - review events. (45mins)
4. Investigate process for next version of software project for new customer - investigation for new process, particularly use of a proxy. (7hrs 15mins)
5. Review the project schedules, adjusted all projects based on actual progress and added a week to software schedules. (5mins)
6. Backup mail locally. (10mins)

Tuesday, February 9, 2016

Today's work on/in the business - Mon 8 February

1. Update my record of time worked. (5mins)
2. Review progress made this week. (5mins)
3. Investigate process for next version of software project for new customer - investigation for new process, particularly use of a proxy. (8hrs 40mins)

Monday, February 8, 2016

Today's work on/in the business - Sun 7 February

1. Update my record of time worked. (5mins)
2. Review progress made this week. (5mins)
3. Investigate process for next version of software project for new customer - investigation for new process, particularly use of a proxy. (55mins)

Then off to watch Dave race and to a friend's for dinner to celebrate another friend's birthday!

Sunday, February 7, 2016

Today's work on/in the business - Sat 6 February

1. Review progress made this week. (10mins)
2. Update my record of time worked. (5mins)
3. Investigate process for next version of software project for new customer - investigation for new process, particularly use of a proxy. (7hrs 45mins)

Saturday, February 6, 2016

Today's work on/in the business - Fri 5 February

1. Update my record of time worked. (5mins)
2. Review progress made this week. (10mins)
3. Investigate process for next version of software project for new customer - investigation for new process, particularly use of a proxy. (8hrs)

Friday, February 5, 2016

Today's work on/in the business - Thurs 4 February

1. Update my record of time worked. (5mins)
2. Review progress made this week. (10mins)
3. Investigate process for next version of software project for new customer - investigation for new process, particularly use of a proxy. (7hrs 55mins)

Thursday, February 4, 2016

Today's work on/in the business - Wed 3 February

1. Update my record of time worked. (5mins)
2. Review progress made this week. (10mins)
3. Investigate process for next version of software project for new customer - investigation for new process, particularly use of a proxy. (7hrs 30mins)

Wednesday, February 3, 2016

Today's work on/in the business - Tues 2 February

1. Investigate process for next version of software project for new customer - investigation for new process, particularly use of a proxy, including catch up phone call. (4hrs)
2. Update my record of time worked. (10mins)
3. Review progress made this week. (5mins)

Plus time to finish sorting out paperwork and shopping with an unhappy car.

Tuesday, February 2, 2016

Today's work on/in the business - Mon 1 February

1. Update my record of time worked. (5mins)
2. Review progress made last week and ensure the schedule is right for this week. (20mins)
3. Review the project schedules, adjusted all projects based on actual progress and added a week to software schedules. (5mins)
4. Backup mail locally. (25mins)
5. Investigate process for next version of software project for new customer - investigation for new process, particularly use of a proxy. (8hrs 15mins)
6. Working on process for new Events setup - review events. (30mins)

Monday, February 1, 2016

Today's work on/in the business - Fri 29 January

1. Update my record of time worked. (5mins)
2. Review progress made this week. (15mins)
3. Investigate process for next version of software project for new customer - investigation for new process, particularly use of a proxy. (5mins)
4. New project - working on some issues reported. (4hrs 40mins)

Friday, January 29, 2016

Today's work on/in the business - Thurs 28 January

1. Update my record of time worked. (5mins)
2. Review progress made this week. (10mins)
3. New project - working on some issues reported. (3hrs 40mins)
4. Investigate process for next version of software project for new customer - investigation for new process, particularly use of a proxy. (45mins)
5. Working on process for new Events setup - review events. (10mins)

Thursday, January 28, 2016

Today's work on/in the business - Wed 27 January

1. Update my record of time worked. (10mins)
2. Review progress made this week. (25mins)
3. Investigate process for next version of software project for new customer - investigation for new process, particularly use of a proxy. (7hrs 10mins)
4. Working on process for new Events setup - review events. (10mins)

Wednesday, January 27, 2016

Today's work on/in the business - Mon 25 January

1. Update my record of time worked. (10mins)
2. Review progress made last week and ensure the schedule is right for this week. (35mins)
3. Review the project schedules, adjusted all projects based on actual progress and added a week to software schedules. (5mins)
4. Backup mail locally. (30mins)
5. Investigate process for next version of software project for new customer - investigation for new process, particularly use of a proxy. (7hrs)

Monday, January 25, 2016

Today's work on/in the business - Fri 22 January

1. Update my record of time worked. (5mins)
2. Review progress made this week. (5mins)
3. Working on process for new Events setup - review events and add regular events. (1hr 25mins)
4. Investigate process for next version of software project for new customer - investigation for new process, particularly use of a proxy. (4hrs 40mins)

Friday, January 22, 2016

Today's work on/in the business - Thurs 21 January

1. Update my record of time worked. (5mins)
2. Review progress made this week. (10mins)
3. Working on process for new Events setup - review events. (35mins)
4. Investigate process for next version of software project for new customer - investigation for new process, particularly use of a proxy. (5hrs 55mins)

Thursday, January 21, 2016

Today's work on/in the business - Wed 20 January

1. Update my record of time worked. (15mins)
2. Review progress made this week. (10mins)
3. New project - request access again to other site, after all possible passwords failed. (15mins)
4. Investigate process for next version of software project for new customer - investigation for new process, particularly use of a proxy. (4hrs 45mins)

Wednesday, January 20, 2016

Today's work on/in the business - Tues 19 January

1. Update my record of time worked. (10mins)
2. Review progress made this week. (5mins)
3. Investigate process for next version of software project for new customer - investigation for new process, particularly use of a proxy. (3hrs 15mins)

(Another hot day with no focus...)

Tuesday, January 19, 2016

Today's work on/in the business - Mon 18 January

1. Update my record of time worked. (5mins)
2. Review progress made last week and ensure the schedule is right for this week. (15mins)
3. Review the project schedules, adjusted all projects based on actual progress and added a week to software schedules. (10mins)
4. New project - call re security testing. (5mins)
5. Call from support customer. (5mins)
6. Investigate process for next version of software project for new customer - investigation for new process, particularly use of a proxy. (3hrs 35mins)
7. Backup mail locally. (15mins)

Monday, January 18, 2016

Today's work on/in the business - Fri 15 January

1. Update my record of time worked. (5mins)
2. Review progress made this week. (5mins)
3. Investigate process for next version of software project for new customer - investigation for new process, particularly use of a proxy. (1hr 15mins)

Friday, January 15, 2016

Today's work on/in the business - Thurs 14 January

1. Update my record of time worked. (5mins)
2. Review progress made this week. (15mins)
3. Working on process for new Events setup - review events. (20mins)
4. Investigate process for next version of software project for new customer - investigation for new process, particularly use of a proxy. (4hrs 5mins)

Thursday, January 14, 2016

Today's work on/in the business - Wed 13 January

1. Update my record of time worked. (5mins)
2. Review progress made this week. (10mins)
3. Investigate process for next version of software project for new customer - investigation for new process, particularly use of a proxy. (3hrs)

It was just TOO hot to think straight and do real work - even with the house shut up all day.

Wednesday, January 13, 2016

Today's work on/in the business - Tues 12 January

1. Update my record of time worked. (5mins)
2. Review progress made this week. (10mins)
3. Investigate process for next version of software project for new customer - investigation for new process, particularly use of a proxy. (9hrs 10mins)

A bit of time spent organising my licence paperwork. Then we went off for a wonderful night of music - a very late night... Then we stayed up while Dave did more work on his laptop, which is really playing up.

Tuesday, January 12, 2016

Today's work on/in the business - Mon 11 January

1. Update my record of time worked. (5mins)
2. Review progress made last week and ensure the schedule is right for this week. (20mins)
3. Review the project schedules, adjusted all projects based on actual progress and added a week to software schedules. (5mins)
4. Backup mail locally. (10mins)
5. Investigate process for next version of software project for new customer - investigation for new process, particularly use of a proxy. (4hrs 50mins)

Monday, January 11, 2016

Today's work on/in the business - Fri 8 January

1. Update my record of time worked. (5mins)
2. Review progress made this week. (5mins)
3. Investigate process for next version of software project for new customer - investigation for new process, particularly use of a proxy. (6hrs 25mins)

Friday, January 8, 2016

Today's work on/in the business - Thurs 7 January

1. Update my record of time worked. (5mins)
2. Review progress made this week. (10mins)
3. Investigate process for next version of software project for new customer - investigation for new process, particularly use of a proxy. (10hrs 40mins)

Thursday, January 7, 2016

Today's work on/in the business - Wed 6 January

1. Update my record of time worked. (10mins)
2. Review progress made this week. (5mins)
3. Investigate process for next version of software project for new customer - investigation for new process, particularly use of a proxy. (8hrs)

Wednesday, January 6, 2016

Today's work on/in the business - Tues 5 January

1. Update my record of time worked. (5mins)
2. Review progress made this week. (10mins)
3. Investigate process for next version of software project for new customer - investigation for new process, particularly use of a proxy. (7hrs 10mins)
4. Working on process for new Events setup - review events. (15mins)

Tuesday, January 5, 2016

Today's work on/in the business - Mon 4 January

1. Update my record of time worked. (5mins)
2. Review progress made last week and ensure the schedule is right for this week. (15mins)
3. Review the project schedules, adjusted all projects based on actual progress and added a week to software schedules. (5mins)
4. Backup mail locally. (10mins)
5. Working on process for new Events setup - review events. (25mins)
6. Accounting - pay a couple of bills. (10mins)
7. Investigate process for next version of software project for new customer - investigation for new process, particularly use of a proxy. (5hrs 45mins)

Monday, January 4, 2016

Today's work on/in the business - Thurs 31 December

1. Update my record of time worked. (5mins)
2. Review progress made this week. (5mins)
3. Investigate process for next version of software project for new customer - investigation for new process, particularly use of a proxy. (5hrs 10mins)

And then another break - it's nice to actually not work for a while!

HAPPY NEW YEAR!