1. Update my record of time worked. (10mins)
2. Investigate process for next version of software project for new customer - investigation for new process, particularly use of a proxy. (7hrs 15mins)
3. Review progress made last week and ensure the schedule is right for this week. (50mins)
4. Work on support customer's server - continue investigation of upgrade issue - find password information. (10mins)
5. Top up mobile phone. (5mins)
6. Working on process for new Events setup - review events and enter regular events. (1hr 30mins)
Tuesday, September 30, 2014
Saturday, September 27, 2014
Today's work on/in the business - Fri 26 September
1. Update my record of time worked. (10mins)
2. Work on support customer's server - continue investigation of upgrade issue - mail and file server setup. (1hr 20mins)
3. Review progress made this week and ensure the schedule is right for next week. (1hr 35mins)
4. Review the project schedules, adjusted all projects based on actual progress and added a week to software schedules. (5mins)
5. Backup my mail locally. (50mins)
6. Topup broadband. (10mins)
7. Investigate process for next version of software project for new customer - investigation for new process, particularly use of a proxy. (2hrs 50mins)
2. Work on support customer's server - continue investigation of upgrade issue - mail and file server setup. (1hr 20mins)
3. Review progress made this week and ensure the schedule is right for next week. (1hr 35mins)
4. Review the project schedules, adjusted all projects based on actual progress and added a week to software schedules. (5mins)
5. Backup my mail locally. (50mins)
6. Topup broadband. (10mins)
7. Investigate process for next version of software project for new customer - investigation for new process, particularly use of a proxy. (2hrs 50mins)
Friday, September 26, 2014
Today's work on/in the business - Thurs 25 September
1. Work on support customer's server - continue investigation of upgrade issue - finally mostly fixing email server. (16hrs 10mins)
2. Update my record of time worked. (5mins)
2. Update my record of time worked. (5mins)
Thursday, September 25, 2014
Today's work on/in the business - Wed 24 September
1. Work on support customer's server - continue investigation of upgrade issue. (14hrs 20mins)
2. Update my record of time worked. (10mins)
3. Read IT blogs. (1hr)
2. Update my record of time worked. (10mins)
3. Read IT blogs. (1hr)
Wednesday, September 24, 2014
Today's work on/in the business - Tues 23 September
1. Work on support customer's server - continue investigation of upgrade issue. (19hrs 25mins)
2. Review progress made this week. (20mins)
Yes - don't ask about the hours - they're real.... Soon this mail server will be running again and we can get some sleep!!
2. Review progress made this week. (20mins)
Yes - don't ask about the hours - they're real.... Soon this mail server will be running again and we can get some sleep!!
Today's work on/in the business - Mon 22 September
1. Work on support customer's server - continue investigation of upgrade issue. (11hrs 15mins)
2. Working on process for new Events setup - review events. (25mins)
2. Working on process for new Events setup - review events. (25mins)
Today's work on/in the business - Sun 21 September
1. Update my record of time worked. (5mins)
2. Review progress made this week. (25mins)
3. Work on support customer's server - continue investigation of upgrade issue. (17hrs)
2. Review progress made this week. (25mins)
3. Work on support customer's server - continue investigation of upgrade issue. (17hrs)
Sunday, September 21, 2014
Today's work on/in the business - Sat 20 September
1. Update my record of time worked. (5mins)
2. Work on support customer's server - continue investigation of upgrade issue. (9hrs)
2. Work on support customer's server - continue investigation of upgrade issue. (9hrs)
Saturday, September 20, 2014
Today's work on/in the business - Fri 19 September
1. Update my record of time worked. (10mins)
2. Review progress made this week. (45mins)
3. Working on process for new Events setup - review events. (35mins)
4. Work on support customer's server - continue investigation of upgrade issue. (9hrs 25mins)
2. Review progress made this week. (45mins)
3. Working on process for new Events setup - review events. (35mins)
4. Work on support customer's server - continue investigation of upgrade issue. (9hrs 25mins)
Friday, September 19, 2014
Today's work on/in the business - Thurs 18 September
1. Update my record of time worked. (10mins)
2. Review progress made this week. (15mins)
3. Work on support customer's server - continue investigation of upgrade issue. (6hrs 35mins)
4. Investigate process for next version of software project for new customer - investigation for new process, particularly use of a proxy. (5hrs 25mins)
2. Review progress made this week. (15mins)
3. Work on support customer's server - continue investigation of upgrade issue. (6hrs 35mins)
4. Investigate process for next version of software project for new customer - investigation for new process, particularly use of a proxy. (5hrs 25mins)
Thursday, September 18, 2014
Today's work on/in the business - Wed 17 September
1. Work on support customer's server - continue investigation of upgrade issue. (12hrs 55mins)
2. Top up mobile phone. (5mins)
3. Top up broadband. (5mins)
4. Update my record of time worked. (5mins)
5. Review progress made this week. (35mins)
2. Top up mobile phone. (5mins)
3. Top up broadband. (5mins)
4. Update my record of time worked. (5mins)
5. Review progress made this week. (35mins)
Wednesday, September 17, 2014
Today's work on/in the business - Tues 16 September
1. Update my record of time worked. (5mins)
2. Review progress made this week. (5mins)
3. Investigate process for next version of software project for new customer - investigation for new process, particularly use of a proxy. (2hrs)
4. Work on support customer's server - continue investigation of upgrade issue. (9hrs)
2. Review progress made this week. (5mins)
3. Investigate process for next version of software project for new customer - investigation for new process, particularly use of a proxy. (2hrs)
4. Work on support customer's server - continue investigation of upgrade issue. (9hrs)
Tuesday, September 16, 2014
Today's work on/in the business - Mon 15 September
1. Update my record of time worked. (5mins)
2. Review progress made this week. (20mins)
3. Investigate process for next version of software project for new customer - investigation for new process, particularly use of a proxy. (8hrs 40mins)
2. Review progress made this week. (20mins)
3. Investigate process for next version of software project for new customer - investigation for new process, particularly use of a proxy. (8hrs 40mins)
Monday, September 15, 2014
Today's work on/in the business - Sun 14 September
1. Work on support customer's server - continue investigation of upgrade issue. (2hrs 50mins)
2. Update my record of time worked. (5mins)
3. Review progress made this week and ensure the schedule is right for next week. (55mins)
4. Review the project schedules, adjusted all projects based on actual progress and added a week to software schedules. (5mins)
5. Backup my mail locally. (1hr 15mins)
2. Update my record of time worked. (5mins)
3. Review progress made this week and ensure the schedule is right for next week. (55mins)
4. Review the project schedules, adjusted all projects based on actual progress and added a week to software schedules. (5mins)
5. Backup my mail locally. (1hr 15mins)
Sunday, September 14, 2014
Today's work on/in the business - Sat 13 September
1. Update my record of time worked. (10mins)
2. Working on process for new Events setup - review events. (5mins)
3. Review progress made this week. (30mins)
4. Investigate process for next version of software project for new customer - investigation for new process, particularly use of a proxy. (30mins)
5. Work on support customer's server - continue investigation of upgrade issue. (30mins)
2. Working on process for new Events setup - review events. (5mins)
3. Review progress made this week. (30mins)
4. Investigate process for next version of software project for new customer - investigation for new process, particularly use of a proxy. (30mins)
5. Work on support customer's server - continue investigation of upgrade issue. (30mins)
Saturday, September 13, 2014
Today's work on/in the business - Fri 12 September
1. Update my record of time worked. (10mins)
2. Review progress made this week. (25mins)
3. Investigate process for next version of software project for new customer - investigation for new process, particularly use of a proxy. (4hrs 5mins)
4. Work on support customer's server - continue investigation of upgrade issue. (2hrs 15mins)
5. Follow up email and phone call re support customer's website - set up static HTML 'coming soon' page and ask for DNS change. (1hr 25mins)
2. Review progress made this week. (25mins)
3. Investigate process for next version of software project for new customer - investigation for new process, particularly use of a proxy. (4hrs 5mins)
4. Work on support customer's server - continue investigation of upgrade issue. (2hrs 15mins)
5. Follow up email and phone call re support customer's website - set up static HTML 'coming soon' page and ask for DNS change. (1hr 25mins)
Friday, September 12, 2014
Today's work on/in the business - Thurs 11 September
1. Update my record of time worked. (5mins)
2. Review progress made this week. (10mins)
3. Investigate process for next version of software project for new customer - investigation for new process, particularly use of a proxy. (7hrs 10mins)
4. Investigate issue with customer's website, then take and download a full backup again. (3hrs 40mins)
2. Review progress made this week. (10mins)
3. Investigate process for next version of software project for new customer - investigation for new process, particularly use of a proxy. (7hrs 10mins)
4. Investigate issue with customer's website, then take and download a full backup again. (3hrs 40mins)
Thursday, September 11, 2014
Today's work on/in the business - Wed 10 September
1. Update my record of time worked. (5mins)
2. Review progress made this week. (10mins)
3. Investigate process for next version of software project for new customer - investigation for new process, particularly use of a proxy. (5hrs 50mins)
4. Run updates on my laptop. (25mins)
2. Review progress made this week. (10mins)
3. Investigate process for next version of software project for new customer - investigation for new process, particularly use of a proxy. (5hrs 50mins)
4. Run updates on my laptop. (25mins)
Wednesday, September 10, 2014
Today's work on/in the business - Tues 9 September
1. Update my record of time worked. (5mins)
2. Review progress made this week. (15mins)
3. Investigate process for next version of software project for new customer - investigation for new process, particularly use of a proxy. (8hrs 10mins)
2. Review progress made this week. (15mins)
3. Investigate process for next version of software project for new customer - investigation for new process, particularly use of a proxy. (8hrs 10mins)
Tuesday, September 9, 2014
Today's work on/in the business - Mon 8 September
1. Update my record of time worked. (15mins)
2. Working on process for new Events setup - cancel an event. (5mins)
3. Review progress made this week. (40mins)
4. Run updates on my laptop. (15mins)
5. Investigate process for next version of software project for new customer - investigation for new process, particularly use of a proxy. (7hrs 30mins)
2. Working on process for new Events setup - cancel an event. (5mins)
3. Review progress made this week. (40mins)
4. Run updates on my laptop. (15mins)
5. Investigate process for next version of software project for new customer - investigation for new process, particularly use of a proxy. (7hrs 30mins)
Monday, September 8, 2014
Today's work on/in the business - Sun 7 September
1. Update my record of time worked. (5mins)
2. Review progress made this week and ensure the schedule is right for next week. (30mins)
3. Review the project schedules, adjusted all projects based on actual progress and added a week to software schedules. (5mins)
4. Backup my mail locally. (30mins)
5. Anti virus and malware scans on both laptops, as this needs to be done regularly to be sure they are clean - running scan on Windows server - reported clean. (3hrs 20mins)
2. Review progress made this week and ensure the schedule is right for next week. (30mins)
3. Review the project schedules, adjusted all projects based on actual progress and added a week to software schedules. (5mins)
4. Backup my mail locally. (30mins)
5. Anti virus and malware scans on both laptops, as this needs to be done regularly to be sure they are clean - running scan on Windows server - reported clean. (3hrs 20mins)
Saturday, September 6, 2014
Today's work on/in the business - Fri 5 September
1. Update my record of time worked. (10mins)
2. Review progress made this week. (15mins)
3. Investigate process for next version of software project for new customer - investigation for new process, particularly use of a proxy. (8hrs)
4. Prospect rang back - put together a proper quote and send to her. (5mins)
2. Review progress made this week. (15mins)
3. Investigate process for next version of software project for new customer - investigation for new process, particularly use of a proxy. (8hrs)
4. Prospect rang back - put together a proper quote and send to her. (5mins)
Friday, September 5, 2014
Today's work on/in the business - Thurs 4 September
1. Update my record of time worked. (5mins)
2. Review progress made this week. (10mins)
3. Investigate process for next version of software project for new customer - investigation for new process, particularly use of a proxy. (7hrs 25mins)
4. Read small business blogs. (1hr 15mins)
5. Working on process for new Events setup - review events. (5mins)
2. Review progress made this week. (10mins)
3. Investigate process for next version of software project for new customer - investigation for new process, particularly use of a proxy. (7hrs 25mins)
4. Read small business blogs. (1hr 15mins)
5. Working on process for new Events setup - review events. (5mins)
Thursday, September 4, 2014
Today's work on/in the business - Wed 3 September
1. Update my record of time worked. (10mins)
2. Review progress made this week. (10mins)
3. Working on process for new Events setup - review events and setup two hosts. (20mins)
4. Follow up email on support customer's website, to organise test setup and ongoing hosting. (5mins)
5. Investigate process for next version of software project for new customer - investigation for new process, particularly use of a proxy. (6hrs 55mins)
2. Review progress made this week. (10mins)
3. Working on process for new Events setup - review events and setup two hosts. (20mins)
4. Follow up email on support customer's website, to organise test setup and ongoing hosting. (5mins)
5. Investigate process for next version of software project for new customer - investigation for new process, particularly use of a proxy. (6hrs 55mins)
Wednesday, September 3, 2014
Today's work on/in the business - Tues 2 September
1. Update my record of time worked. (5mins)
2. Review progress made this week. (10mins)
3. Working on process for new Events setup - review events. (2hrs)
4. Investigate process for next version of software project for new customer - investigation for new process, particularly use of a proxy. (35mins)
2. Review progress made this week. (10mins)
3. Working on process for new Events setup - review events. (2hrs)
4. Investigate process for next version of software project for new customer - investigation for new process, particularly use of a proxy. (35mins)
Tuesday, September 2, 2014
Today's work on/in the business - Mon 1 September
1. Update my record of time worked. (10mins)
2. Review progress made last week and ensure the schedule is right for this week. (20mins)
3. Review the project schedules, adjusted all projects based on actual progress and added a week to software schedules. (5mins)
4. Investigate more detail on support customer's website, to organise update. (10mins)
5. Invoice reconciliation - draft email and prepare statement. (1hr 5mins)
6. Work on support customer's server - test mail access. (45mins)
7. Determine whether we met the KPIs (Key Performance Indicators) for August 2014. Thankfully, we met most of them - the obvious one that failed being my requirement to exercise and we need to work on contacting new prospects too (still). Sadly, networking also lost out again last month. (15mins)
8. Accounting. (2hrs)
2. Review progress made last week and ensure the schedule is right for this week. (20mins)
3. Review the project schedules, adjusted all projects based on actual progress and added a week to software schedules. (5mins)
4. Investigate more detail on support customer's website, to organise update. (10mins)
5. Invoice reconciliation - draft email and prepare statement. (1hr 5mins)
6. Work on support customer's server - test mail access. (45mins)
7. Determine whether we met the KPIs (Key Performance Indicators) for August 2014. Thankfully, we met most of them - the obvious one that failed being my requirement to exercise and we need to work on contacting new prospects too (still). Sadly, networking also lost out again last month. (15mins)
8. Accounting. (2hrs)
Monday, September 1, 2014
Today's work on/in the business - Sun 31 August
1. Update my record of time worked. (5mins)
2. Working on process for new Events setup - review events and discuss mail issue. (20mins)
3. Backup my mail locally - trying to leave it running long enough to actually download the bodies of the emails. (8hrs 45mins)
2. Working on process for new Events setup - review events and discuss mail issue. (20mins)
3. Backup my mail locally - trying to leave it running long enough to actually download the bodies of the emails. (8hrs 45mins)
Subscribe to: