1. Working on process for new Events setup - review events. (5mins)
2. Update my record of time worked. (5mins)
3. Review progress made last week and ensure the schedule is right for this week. (1hr 5mins)
4. Review the project schedules, adjusted all projects based on actual progress and added 1 week to software schedules. (5mins)
5. Accounting. (3hrs)
6. BAS. (40mins)
Friday, February 28, 2014
Thursday, February 27, 2014
Today's work on/in the business - Wed 26 Feb
1. Update my record of time worked. (5mins)
2. Investigate process for next version of software project for new customer - investigation for new process. (5hrs 15mins)
3. Working on process for new Events setup - review events and enter regular events. (1hr 40mins)
2. Investigate process for next version of software project for new customer - investigation for new process. (5hrs 15mins)
3. Working on process for new Events setup - review events and enter regular events. (1hr 40mins)
Wednesday, February 26, 2014
Today's work on/in the business - Tues 25 Feb
1. Update my record of time worked. (5mins)
2. Investigate process for next version of software project for new customer - investigation for new process. (2hrs 5mins)
Most of the afternoon lost to trying to break into our car after the keys were accidentally locked inside - and looking for the other sets that are missing and must be somewhere in the house!
2. Investigate process for next version of software project for new customer - investigation for new process. (2hrs 5mins)
Most of the afternoon lost to trying to break into our car after the keys were accidentally locked inside - and looking for the other sets that are missing and must be somewhere in the house!
Tuesday, February 25, 2014
Today's work on/in the business - Mon 24 Feb
1. Update my record of time worked. (10mins)
2. Investigate process for next version of software project for new customer - investigation for new process. (8hrs 20mins)
3. Assist with server investigation for support customer. (1hr 10mins)
4. Investigate issue with site redirection for website customer. (20mins)
5. Review progress made this week. (15mins)
2. Investigate process for next version of software project for new customer - investigation for new process. (8hrs 20mins)
3. Assist with server investigation for support customer. (1hr 10mins)
4. Investigate issue with site redirection for website customer. (20mins)
5. Review progress made this week. (15mins)
Monday, February 24, 2014
Today's work on/in the business - Fri 21 Feb
1. Update my record of time worked. (5mins)
2. Investigate issue with form completion for website customer. (30mins)
2. Investigate issue with form completion for website customer. (30mins)
Friday, February 21, 2014
Today's work on/in the business - Thurs 20 Feb
1. Update my record of time worked. (5mins)
2. Review progress made last week and ensure the schedule is right for this week. (1hr 25mins)
3. Review the project schedules, adjusted all projects based on actual progress and added 1 week to software schedules. (5mins)
4. Backup my mail locally. (1hr 30mins)
5. Investigate process for next version of software project for new customer - investigation for new process. (2hrs 50mins)
2. Review progress made last week and ensure the schedule is right for this week. (1hr 25mins)
3. Review the project schedules, adjusted all projects based on actual progress and added 1 week to software schedules. (5mins)
4. Backup my mail locally. (1hr 30mins)
5. Investigate process for next version of software project for new customer - investigation for new process. (2hrs 50mins)
Thursday, February 20, 2014
Today's work on/in the business - Wed 19 Feb
1. Update my record of time worked. (10mins)
2. Investigate process for next version of software project for new customer - investigation for new process. (9hrs 40mins)
3. Review progress made this week. (25mins)
2. Investigate process for next version of software project for new customer - investigation for new process. (9hrs 40mins)
3. Review progress made this week. (25mins)
Wednesday, February 19, 2014
Today's work on/in the business - Tues 18 Feb
1. Investigate process for next version of software project for new customer - investigation for new process, as well as updating the documentation. (7hrs 20mins)
2. Update my record of time worked. (5mins)
3. Review progress made this week. (20mins)
4. Assist with investigation for support customer. (45mins)
2. Update my record of time worked. (5mins)
3. Review progress made this week. (20mins)
4. Assist with investigation for support customer. (45mins)
Tuesday, February 18, 2014
Today's work on/in the business - Mon 17 Feb
1. Update my record of time worked. (10mins)
2. Review progress made this week. (20mins)
3. Investigate process for next version of software project for new customer - investigation for new process. (7hrs 15mins)
2. Review progress made this week. (20mins)
3. Investigate process for next version of software project for new customer - investigation for new process. (7hrs 15mins)
Monday, February 17, 2014
Today's work on/in the business - Sun 16 Feb
1. Update my record of time worked. (5mins)
2. Investigate process for next version of software project for new customer - investigation for new process. (3hrs 50mins)
2. Investigate process for next version of software project for new customer - investigation for new process. (3hrs 50mins)
Sunday, February 16, 2014
Today's work on/in the business - Fri 14 Feb
1. Update my record of time worked. (10mins)
2. Review progress made this week. (15mins)
3. Investigate process for next version of software project for new customer - investigation for new process. (2hrs 10mins)
Time spent assisting with work on the car. And then a bike ride.
Saturday was filled with music!
2. Review progress made this week. (15mins)
3. Investigate process for next version of software project for new customer - investigation for new process. (2hrs 10mins)
Time spent assisting with work on the car. And then a bike ride.
Saturday was filled with music!
Friday, February 14, 2014
Today's work on/in the business - Thurs 13 Feb
1. Update my record of time worked. (5mins)
2. Investigate process for next version of software project for new customer - investigation for new process. (8hrs 30mins)
2. Investigate process for next version of software project for new customer - investigation for new process. (8hrs 30mins)
Thursday, February 13, 2014
Today's work on/in the business - Wed 12 Feb
1. Backup my mail locally. (10mins)
2. Update my record of time worked. (15mins)
3. Assist with investigation of setup for web customer. (10mins)
4. Run Windows updates on my laptop. (55mins)
5. Top up mobile phone. (5mins)
6. Investigate process for next version of software project for new customer - investigation for new process. (8hrs 35mins)
7. Review progress made this week. (10mins)
2. Update my record of time worked. (15mins)
3. Assist with investigation of setup for web customer. (10mins)
4. Run Windows updates on my laptop. (55mins)
5. Top up mobile phone. (5mins)
6. Investigate process for next version of software project for new customer - investigation for new process. (8hrs 35mins)
7. Review progress made this week. (10mins)
Wednesday, February 12, 2014
Today's work on/in the business - Tues 11 Feb
1. Update my record of time worked. (10mins)
2. Review progress made last week and ensure the schedule is right for this week. (1hr)
3. Review the project schedules, adjusted all projects based on actual progress and added 1 week to software schedules. (5mins)
4. Work on WordPress plugin changes for new customer - test and install another requested change. (1hr)
5. Investigate process for next version of software project for new customer - investigation for new process. (5hrs 55mins)
2. Review progress made last week and ensure the schedule is right for this week. (1hr)
3. Review the project schedules, adjusted all projects based on actual progress and added 1 week to software schedules. (5mins)
4. Work on WordPress plugin changes for new customer - test and install another requested change. (1hr)
5. Investigate process for next version of software project for new customer - investigation for new process. (5hrs 55mins)
Tuesday, February 11, 2014
Today's work on/in the business - Mon 10 Feb
1. Update my record of time worked. (5mins)
2. Investigate process for next version of software project for new customer - investigation for new process. (8hrs 10mins)
3. Review progress made this week. (25mins)
2. Investigate process for next version of software project for new customer - investigation for new process. (8hrs 10mins)
3. Review progress made this week. (25mins)
Monday, February 10, 2014
Today's work on/in the business - Sun 9 Feb
1. Update my record of time worked. (5mins)
2. Investigate process for next version of software project for new customer - investigation for new process. (1hr 20mins)
2. Investigate process for next version of software project for new customer - investigation for new process. (1hr 20mins)
Sunday, February 9, 2014
Today's work on/in the business - Sat 8 Feb
1. Update my record of time worked. (5mins)
2. Malware scans on my laptop, as this needs to be done regularly to be sure it is clean - fourth one run and reported clean. (8hrs 5mins)
2. Malware scans on my laptop, as this needs to be done regularly to be sure it is clean - fourth one run and reported clean. (8hrs 5mins)
Saturday, February 8, 2014
Today's work on/in the business - Fri 7 Feb
1. Update my record of time worked. (5mins)
2. Working on process for new Events setup - review events. (20mins)
3. Review progress made this week. (40mins)
4. Investigate process for next version of software project for new customer - apply design changes to new process. (5hrs 40mins)
Plus some time spent helping to put a car engine back together...
2. Working on process for new Events setup - review events. (20mins)
3. Review progress made this week. (40mins)
4. Investigate process for next version of software project for new customer - apply design changes to new process. (5hrs 40mins)
Plus some time spent helping to put a car engine back together...
Friday, February 7, 2014
Today's work on/in the business - Thurs 6 Feb
1. Update my record of time worked. (5mins)
2. Investigate process for next version of software project for new customer - apply design changes to new process. (6hrs 55mins)
3. Review progress made this week. (15mins)
2. Investigate process for next version of software project for new customer - apply design changes to new process. (6hrs 55mins)
3. Review progress made this week. (15mins)
Thursday, February 6, 2014
Today's work on/in the business - Wed 5 Feb
1. Update my record of time worked. (10mins)
2. Anti virus scans on my laptop, as this needs to be done regularly to be sure it is clean - third one finished and reported clean. (25mins)
3. Investigate process for next version of software project for new customer - apply design changes to new process. (9hrs 5mins)
4. Review progress made this week. (40mins)
2. Anti virus scans on my laptop, as this needs to be done regularly to be sure it is clean - third one finished and reported clean. (25mins)
3. Investigate process for next version of software project for new customer - apply design changes to new process. (9hrs 5mins)
4. Review progress made this week. (40mins)
Wednesday, February 5, 2014
Today's work on/in the business - Tues 4 Feb
1. Update my record of time worked. (10mins)
2. Review progress made this week. (50mins)
3. Investigate process for next version of software project for new customer - investigation for new process. (7hrs)
4. Anti virus scans on my laptop, as this needs to be done regularly to be sure it is clean - third one running. (4hrs 5mins)
2. Review progress made this week. (50mins)
3. Investigate process for next version of software project for new customer - investigation for new process. (7hrs)
4. Anti virus scans on my laptop, as this needs to be done regularly to be sure it is clean - third one running. (4hrs 5mins)
Tuesday, February 4, 2014
Today's work on/in the business - Mon 3 Feb
1. Update my record of time worked. (10mins)
2. Anti virus scans on my laptop, as this needs to be done regularly to be sure it is clean - first two finished and reported clean. (7hrs 5mins)
3. Investigate process for next version of software project for new customer - investigation for new process. (1hr 35mins)
4. Assist with setup of test website for upgrade for website customer. (5mins)
2. Anti virus scans on my laptop, as this needs to be done regularly to be sure it is clean - first two finished and reported clean. (7hrs 5mins)
3. Investigate process for next version of software project for new customer - investigation for new process. (1hr 35mins)
4. Assist with setup of test website for upgrade for website customer. (5mins)
Monday, February 3, 2014
Today's work on/in the business - Sun 2 Feb
1. Update my record of time worked. (5mins)
2. Review progress made this week and ensure the schedule is right for next week. (1hr 5mins)
3. Determine whether we met the KPIs (Key Performance Indicators) for December 2013 and January 2014. Thankfully, we met most of them - the obvious one that failed being my requirement to exercise (although I have been riding more) and we need to work on contacting new prospects too (still). The online networking KPI failed both months, as I have been tied up in this project. (15mins)
4. Review the project schedules, adjusted all projects based on actual progress and added 1 week to software schedules. (5mins)
5. Backup my mail locally. (1hr 50mins)
6. Anti virus scans on my laptop, as this needs to be done regularly to be sure it is clean - first two running. (4hrs 45mins)
2. Review progress made this week and ensure the schedule is right for next week. (1hr 5mins)
3. Determine whether we met the KPIs (Key Performance Indicators) for December 2013 and January 2014. Thankfully, we met most of them - the obvious one that failed being my requirement to exercise (although I have been riding more) and we need to work on contacting new prospects too (still). The online networking KPI failed both months, as I have been tied up in this project. (15mins)
4. Review the project schedules, adjusted all projects based on actual progress and added 1 week to software schedules. (5mins)
5. Backup my mail locally. (1hr 50mins)
6. Anti virus scans on my laptop, as this needs to be done regularly to be sure it is clean - first two running. (4hrs 45mins)
Sunday, February 2, 2014
Today's work on/in the business - Sat 1 Feb
1. Comment on the last blog post and cross post on Facebook. (5mins)
2. Update my record of time worked. (20mins)
2. Update my record of time worked. (20mins)
Saturday, February 1, 2014
Today's work on/in the business - Fri 31 Jan
1. Update my record of time worked. (5mins)
2. Work on WordPress plugin changes for new customer - test and install final requested changes. (1hr 25mins)
3. Investigate process for next version of software project for new customer - investigation for new process. (4hrs 40mins)
2. Work on WordPress plugin changes for new customer - test and install final requested changes. (1hr 25mins)
3. Investigate process for next version of software project for new customer - investigation for new process. (4hrs 40mins)
Subscribe to: