1. Update my record of time worked. (5mins)
2. Review progress made this week. (30mins)
3. Working on process for new Events setup - review events and enter regular events.
(1hr 35mins)
4. Investigate process for next version of software project for new
customer - investigation for new process, particularly use of a proxy.
(6hrs 40mins)
Thursday, June 30, 2016
Wednesday, June 29, 2016
Today's work on/in the business - Tues 28 June
1. Update my record of time worked. (5mins)
2. Review progress made this week. (10mins)
3. Investigate process for next version of software project for new customer - investigation for new process, particularly use of a proxy. (7hrs 25mins)
4. Invoice reconciliation - talk to one customer and send out email. (25mins)
2. Review progress made this week. (10mins)
3. Investigate process for next version of software project for new customer - investigation for new process, particularly use of a proxy. (7hrs 25mins)
4. Invoice reconciliation - talk to one customer and send out email. (25mins)
Tuesday, June 28, 2016
Today's work on/in the business - Mon 27 June
1. Update my record of time worked. (5mins)
2. Review progress made last week and ensure the schedule is right for this week. (20mins)
3. Review the project schedules, adjusted all projects based on actual progress and added a week to software schedules. (5mins)
4. Backup mail locally - both laptops. (30mins)
5. Invoice reconciliation - find one email address, update one invoice, send out invoices to two customers. (20mins)
6. Investigate process for next version of software project for new customer - investigation for new process, particularly use of a proxy. (6hrs 15mins)
2. Review progress made last week and ensure the schedule is right for this week. (20mins)
3. Review the project schedules, adjusted all projects based on actual progress and added a week to software schedules. (5mins)
4. Backup mail locally - both laptops. (30mins)
5. Invoice reconciliation - find one email address, update one invoice, send out invoices to two customers. (20mins)
6. Investigate process for next version of software project for new customer - investigation for new process, particularly use of a proxy. (6hrs 15mins)
Monday, June 27, 2016
Today's work on/in the business - Fri 24 June
1. Update my record of time worked. (5mins)
2. Review progress made this week. (10mins)
3. Investigate process for next version of software project for new customer - investigation for new process, particularly use of a proxy. (9hrs 40mins)
2. Review progress made this week. (10mins)
3. Investigate process for next version of software project for new customer - investigation for new process, particularly use of a proxy. (9hrs 40mins)
Friday, June 24, 2016
Today's work on/in the business - Thurs 23 June
1. Update my record of time worked. (5mins)
2. Review progress made this week. (5mins)
3. Investigate process for next version of software project for new customer - investigation for new process, particularly use of a proxy. (8hrs)
2. Review progress made this week. (5mins)
3. Investigate process for next version of software project for new customer - investigation for new process, particularly use of a proxy. (8hrs)
Thursday, June 23, 2016
Today's work on/in the business - Wed 22 June
1. Update my record of time worked. (5mins)
2. Review progress made this week. (5mins)
3. Investigate process for next version of software project for new customer - investigation for new process, particularly use of a proxy. (8hrs 35mins)
2. Review progress made this week. (5mins)
3. Investigate process for next version of software project for new customer - investigation for new process, particularly use of a proxy. (8hrs 35mins)
Wednesday, June 22, 2016
Today's work on/in the business - Tues 21 June
1. Update my record of time worked. (5mins)
2. Review progress made this week. (5mins)
3. Investigate process for next version of software project for new customer - investigation for new process, particularly use of a proxy. (9hrs 30mins)
2. Review progress made this week. (5mins)
3. Investigate process for next version of software project for new customer - investigation for new process, particularly use of a proxy. (9hrs 30mins)
Tuesday, June 21, 2016
Today's work on/in the business - Mon 20 June
1. Update my record of time worked. (5mins)
2. Review progress made last week and ensure the schedule is right for this week. (10mins)
3. Review the project schedules, adjusted all projects based on actual progress and added a week to software schedules. (5mins)
4. Backup mail locally. (10mins)
5. Investigate process for next version of software project for new customer - investigation for new process, particularly use of a proxy. (7hrs 35mins)
2. Review progress made last week and ensure the schedule is right for this week. (10mins)
3. Review the project schedules, adjusted all projects based on actual progress and added a week to software schedules. (5mins)
4. Backup mail locally. (10mins)
5. Investigate process for next version of software project for new customer - investigation for new process, particularly use of a proxy. (7hrs 35mins)
Monday, June 20, 2016
Today's work on/in the business - Fri 17 June
1. Update my record of time worked. (10mins)
2. Review progress made this week. (10mins)
3. Top up mobile broadband. (5mins)
4. Investigate process for next version of software project for new customer - investigation for new process, particularly use of a proxy. (8hrs 55mins)
2. Review progress made this week. (10mins)
3. Top up mobile broadband. (5mins)
4. Investigate process for next version of software project for new customer - investigation for new process, particularly use of a proxy. (8hrs 55mins)
Friday, June 17, 2016
Today's work on/in the business - Thurs 16 June
1. Investigate process for next version of software project for new
customer - investigation for new process, particularly use of a proxy.
(6hrs 35mins)
2. Update my record of time worked. (10mins)
3. Review progress made this week. (10mins)
4. Working on process for new Events setup - review events. (5mins)
2. Update my record of time worked. (10mins)
3. Review progress made this week. (10mins)
4. Working on process for new Events setup - review events. (5mins)
Thursday, June 16, 2016
Today's work on/in the business - Wed 15 June
1. Investigate process for next version of software project for new
customer - investigation for new process, particularly use of a proxy.
(8hrs 40mins)
2. Update my record of time worked. (10mins)
3. Review progress made this week. (10mins)
2. Update my record of time worked. (10mins)
3. Review progress made this week. (10mins)
Wednesday, June 15, 2016
Today's work on/in the business - Tues 14 June
1. Update my record of time worked. (5mins)
2. Review progress made this week. (5mins)
3. Working on process for new Events setup - review events. (20mins)
4. Investigate process for next version of software project for new customer - investigation for new process, particularly use of a proxy. (3hrs 40mins)
2. Review progress made this week. (5mins)
3. Working on process for new Events setup - review events. (20mins)
4. Investigate process for next version of software project for new customer - investigation for new process, particularly use of a proxy. (3hrs 40mins)
Tuesday, June 14, 2016
Today's work on/in the business - Mon 13 June
1. Update my record of time worked. (5mins)
2. Review progress made last week and ensure the schedule is right for this week. (20mins)
3. Review the project schedules, adjusted all projects based on actual progress and added a week to software schedules. (5mins)
4. Backup mail locally. (5mins)
5. Accounting - bring recording up to date. (1hr 35mins)
2. Review progress made last week and ensure the schedule is right for this week. (20mins)
3. Review the project schedules, adjusted all projects based on actual progress and added a week to software schedules. (5mins)
4. Backup mail locally. (5mins)
5. Accounting - bring recording up to date. (1hr 35mins)
Monday, June 13, 2016
Today's work on/in the business - Fri 10 June
1. Update my record of time worked. (10mins)
2. Review progress made this week. (10mins)
3. Investigate process for next version of software project for new customer - investigation for new process, particularly use of a proxy. (7hrs 15mins)
4. Work on our server - upgrade of Ubuntu broke a couple of things, which needed to be addressed as soon as possible. (2hrs 20mins)
2. Review progress made this week. (10mins)
3. Investigate process for next version of software project for new customer - investigation for new process, particularly use of a proxy. (7hrs 15mins)
4. Work on our server - upgrade of Ubuntu broke a couple of things, which needed to be addressed as soon as possible. (2hrs 20mins)
Friday, June 10, 2016
Today's work on/in the business - Thurs 9 June
1. Update my record of time worked. (5mins)
2. Review progress made this week. (10mins)
3. Investigate process for next version of software project for new customer - investigation for new process, particularly use of a proxy. (7hrs 40mins)
2. Review progress made this week. (10mins)
3. Investigate process for next version of software project for new customer - investigation for new process, particularly use of a proxy. (7hrs 40mins)
Thursday, June 9, 2016
Today's work on/in the business - Wed 8 June
1. Update my record of time worked. (5mins)
2. Review progress made this week. (5mins)
3. Investigate process for next version of software project for new customer - investigation for new process, particularly use of a proxy. (7hrs 45mins)
2. Review progress made this week. (5mins)
3. Investigate process for next version of software project for new customer - investigation for new process, particularly use of a proxy. (7hrs 45mins)
Wednesday, June 8, 2016
Today's work on/in the business - Tues 7 June
1. Update my record of time worked. (5mins)
2. Investigate process for next version of software project for new customer - investigation for new process, particularly use of a proxy. (12hrs 15mins)
3. Review progress made this week. (15mins)
2. Investigate process for next version of software project for new customer - investigation for new process, particularly use of a proxy. (12hrs 15mins)
3. Review progress made this week. (15mins)
Tuesday, June 7, 2016
Today's work on/in the business - Mon 6 June
1. Update my record of time worked. (5mins)
2. Review progress made last week and ensure the schedule is right for this week. (15mins)
3. Review the project schedules, adjusted all projects based on actual progress and added a week to software schedules. (5mins)
4. Backup mail locally. (10mins)
5. Investigate process for next version of software project for new customer - investigation for new process, particularly use of a proxy. (7hrs 20mins)
2. Review progress made last week and ensure the schedule is right for this week. (15mins)
3. Review the project schedules, adjusted all projects based on actual progress and added a week to software schedules. (5mins)
4. Backup mail locally. (10mins)
5. Investigate process for next version of software project for new customer - investigation for new process, particularly use of a proxy. (7hrs 20mins)
Monday, June 6, 2016
Today's work on/in the business - Fri 3 June
1. Investigate process for next version of software project for new
customer - investigation for new process, particularly use of a proxy.
(7hrs 20mins)
2. Update my record of time worked. (5mins)
3. Review progress made this week. (5mins)
2. Update my record of time worked. (5mins)
3. Review progress made this week. (5mins)
Friday, June 3, 2016
Today's work on/in the business - Thurs 2 June
1. Update my record of time worked. (10mins)
2. Review progress made this week. (15mins)
3. Investigate process for next version of software project for new customer - investigation for new process, particularly use of a proxy. (8hrs 50mins)
2. Review progress made this week. (15mins)
3. Investigate process for next version of software project for new customer - investigation for new process, particularly use of a proxy. (8hrs 50mins)
Thursday, June 2, 2016
Today's work on/in the business - Wed 1 June
1. Update my record of time worked. (10mins)
2. Review progress made this week. (10mins)
3. Working on process for new Events setup - review events. (25mins)
4. Investigate process for next version of software project for new customer - investigation for new process, particularly use of a proxy. (7hrs 45mins)
2. Review progress made this week. (10mins)
3. Working on process for new Events setup - review events. (25mins)
4. Investigate process for next version of software project for new customer - investigation for new process, particularly use of a proxy. (7hrs 45mins)
Wednesday, June 1, 2016
Today's work on/in the business - Tues 31 May
1. Update my record of time worked. (10mins)
2. Review progress made this week. (10mins)
3. Working on process for new Events setup - review events. (25mins)
4. Investigate process for next version of software project for new customer - investigation for new process, particularly use of a proxy. (11hrs 15mins)
2. Review progress made this week. (10mins)
3. Working on process for new Events setup - review events. (25mins)
4. Investigate process for next version of software project for new customer - investigation for new process, particularly use of a proxy. (11hrs 15mins)
Subscribe to: